Constellation Energy data center (East Coventry Township, near Limerick nuclear plant)

Also called: Constellation Energy Limerick Data Campus

Constellation Energy, which owns the Limerick nuclear plant, asked East Coventry Township to allow data centers on land it owns near Route 724. The planning commission recommended saying no, and Constellation withdrew the request in February 2026.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled Constellation withdrew its zoning change request on Feb. 17, 2026; the March 9 hearing was cancelled. The township planning commission had recommended against it in Dec. 2025.

❓ 3 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (Feb 17, 2026): Constellation withdrew its application (BOS-25-002) for data center zoning changes; the March 9, 2026 hearing was cancelled.

What we know

  • 📍 WhereConstellation-owned land off Fricks Lock Road and Sanatoga Road, across the Schuylkill River from the Limerick plant, East Coventry Township, Chester County
  • 🏢 CompanyConstellation Energy
  • 🔌 Where the power comes fromNear Constellation's Limerick nuclear plant

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • What did the planning commission recommend, and has the board voted? 🙋 I'll find out ·
  • How many buildings and megawatts? 🙋 I'll find out ·
  • Would it take power directly from the nuclear plant? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.

    What happened so far

    • Dec 2025
      Township planning commission voted 4-0 to recommend that supervisors reject the zoning changes (reported by trackers; not yet confirmed in minutes).
    • Feb 17, 2026
      Constellation withdrew its application (BOS-25-002) for data center zoning changes; the March 9, 2026 hearing was cancelled.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. 1.4 million sq ft data center campus planned outside Philadelphia, Pennsylvania · DatacenterDynamics · Jan 2026
    2. Constellation Energy Limerick Data Campus · More Than Just Parks Data Center Tracker · Jan 20, 2026
    3. Community Calendar, October 2026 · East Coventry Township · Oct 6, 2026
    4. Notice: Constellation Energy Generation withdraws application BOS-25-002 · East Coventry Township · Feb 17, 2026
    5. Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
    6. DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026
    7. Chester County parcels (Constellation Energy Generation LLC parcels in East Coventry, largest 18-2-14, 65.9 acres, 519 Fricks Lock Rd) · Chester County via PASDA · Oct 8, 2026