No project in Canfield Township, but 5 nearby
Who decides here: the Township Trustees of Canfield Township votes on zoning. Many Ohio townships have their own zoning. Where a township has none, the county decides.
Nearby (within 15 miles)
Possible data center at former McDonald Steel site
McDonald, Trumbull County
350 acres
π Sept 15, 2026: Oppidan held a public question-and-answer meeting at McDonald High School.
Proposedabout 10 miles awayBitdeer data center at former Niles power plant site
Weathersfield, Trumbull County
42.6 acres
π May 2026: Niles City Council passed a 180-day pause on data centers. Weathersfield trustees passedβ¦
Proposedabout 11 miles awayBristolville 25 data center campus (Lordstown)
Lordstown, Trumbull County
133 acres
π June 15, 2026: Public hearing set on extending the pause by another 180 days.
Being builtabout 12 miles awaySoftBank Stargate data center at former GM Lordstown plant
Lordstown, Trumbull County
for OpenAI (Stargate project with SoftBank and Oracle)
π Oct 2025: Crews began clearing the old parking lot in front of the plant for the data center.
Stopped or cancelledabout 14 miles awayCrane Data Centers 'Project Milo' (Hubbard)
Hubbard, Trumbull County
π July 6, 2026: Residents turned in a petition to put a permanent data center ban on the November ballot.
What you can do
- Get told first.
We'll email you if anything changes in Canfield Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Ohio Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.