1 data center project in Augusta Charter Township
Who decides here: the Township Board of Augusta Charter Township votes on zoning. The Washtenaw County may review big projects too.
In Augusta Charter Township
Nearby (within 15 miles)
University of Michigan / Los Alamos computing center, Ypsilanti Township
Ypsilanti Township, Washtenaw County
144 acres Β· for University of Michigan and Los Alamos National Laboratory
π Aug 11, 2026: U-M confirmed the Textile Road site.
Stopped or cancelledabout 7 miles awaySansone Group data center on Toyota land, York Township
York Township, Washtenaw County
412 acres
π March 2026: Toyota was told Sansone Group was withdrawing from the land deal.
Approved, not built yetabout 8 miles awayGoogle data center (Project Cannoli), Van Buren Township
Van Buren Township, Wayne County
282 acres Β· for Google
π Oct 2, 2026: State utility regulators (MPSC) voted 3-0 to approve DTE's 20-year power contracts with β¦
Stopped or cancelledabout 13 miles awayProject Ironwood, Dundee Township
Dundee, Monroe County
750 acres
π Oct 7, 2025: Village of Dundee shelved a pre-agreement with Cloverleaf for water and sewer service.
Being builtabout 13 miles awayStargate data center campus ("The Barn"), Saline Township
Saline, Washtenaw County
250 acres Β· for OpenAI and Oracle
π Dec 18, 2025: MPSC approved DTE's power contracts with conditions, without a full contested case.
Local votes and rules
π³οΈ Election
Residents tried to recall all seven township board members over the rezoning vote. The county clerk rejected the petitions on a technical error in circulator addresses, so no recall vote in November 2026. A recall vote could still come in May 2027.
π Other Β· Washtenaw County
Washtenaw County commissioners passed a resolution praising towns that paused data centers and urging others to do the same. They also backed a state bill to take back $100 million in state money for the University of Michigan and Los Alamos data center.
πΊοΈ Zoning change
The township board voted to rezone 522 acres of farmland to industrial for a $1 billion Thor Equities data center, against its planning commission's advice. Voters overturned it in August 2026.
What you can do
- Get told first.
We'll email you if anything changes in Augusta Charter Township. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Augusta Charter Township: DTE Electric Company (company) or Village of Clinton (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Michigan.