Stargate data center campus ("The Barn"), Saline Township
Also called: The Barn, Stargate Michigan
OpenAI, Oracle and Related Digital are building a 1.4-gigawatt AI data center on about 250 acres of a 575-acre farm site in Saline Township. The township first said no, was sued, and then settled. The settlement bans water cooling, limits noise to 55 decibels and pays $14 million into local funds.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Board of Saline Township.
Where things stand: Being built Under construction since late 2025 after a court settlement with the township and state approval of the power contracts.
❓ 4 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Nov 2026): Township trustees unanimously reaffirmed a 12-year, 50% tax break for the data center and moved to set up an Industrial Development District for it, despite residents' objections that legal steps were skipped.
What we know
- 📍 WhereFarmland on the north side of Michigan Avenue (US-12) in Saline Township; entrance by the old red barn, Saline, Washtenaw County
- 🏢 CompanyRelated Digital
- 🏛️ Owned byRelated Companies
- 👤 Built forOpenAI and Oracle
- 🌳 Size250 acres
- ⚡ Power it needs1,400 megawatts (about as much as 1,120,000 homes)
- 🔌 Where the power comes fromDTE Energy; Oracle must add 1.4 gigawatts of battery storage within 15 years
- 💧 Waterits own well and waste treatment, per the settlement
- ❄️ Coolingclosed-loop cooling; evaporative water cooling is not allowed under the court settlement
- 💵 Cost$16 billion
- 👷 Jobs promised450
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will the on-site well use per day? 🙋 I'll find out ·
- Will new power lines or substations be built for the site? 🙋 I'll find out ·
- Fortune reported about 475 more acres in nearby Bridgewater Township are part of the campus. What is planned there? 🙋 I'll find out ·
- Will EGLE approve the permit to release treated sewage from the campus into the Saline River, and with what limits? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: OpenStreetMap maps 'The Barn Data Center' as a construction site of about 550 acres on the north side of Michigan Avenue in Saline Township. The pin is the middle of that area.
What happened so far
- Sept 10, 2025Township board voted 4-1 to deny the rezoning.
- Sept 12, 2025Related Digital sued the township, calling the denial exclusionary zoning.
- Oct 15, 2025A settlement (consent judgment) was filed in Washtenaw County court, allowing the data center with conditions.
- Nov 2025Site work began weeks after the township's rejection vote.
- Dec 3, 2025State utility regulators (MPSC) held a public hearing on DTE's power contracts.
- Dec 18, 2025MPSC approved DTE's power contracts with conditions, without a full contested case.
- Oct 21, 2026The state environment agency (EGLE) held a public hearing on a permit for an on-site plant that would clean the campus's sewage (from bathrooms and kitchens) and release it into the Saline River. Written comments closed Oct. 23. Cooling water is not covered and would be taken off site.
- Nov 2026Township trustees unanimously reaffirmed a 12-year, 50% tax break for the data center and moved to set up an Industrial Development District for it, despite residents' objections that legal steps were skipped.
Local votes and rules
⚖️ Court case
A judge refused a nearby resident's request to join the case and undo the Saline Township settlement. The judge said the request came too late and the board did approve the deal in a public vote. The resident's lawyer said they were looking at next steps.
🤝 Agreement with the company
The township settled the lawsuit and the data center was allowed. Terms: a 55-decibel noise limit, no water-based cooling, no expansion, about 200 acres kept as open land, plus $4 million for farmland, $2 million for a community fund and $8 million for fire services. A resident later asked the court to throw it out, saying the vote was not public.
⚖️ Court case
Developer Related Digital and the landowners sued Saline Township, saying the denial was 'exclusionary zoning'. The case ended with a consent judgment (a court-approved settlement) in October 2025.
✋ Turned down
The township board voted 4-1 against rezoning farmland for a large data center. The developer sued two days later, and the township then settled (see the agreement record).
Drag the slider to compare the land before and now.
Where this comes from
- Saline Township settles with data center developer: 'Lesser of two evils' · Planet Detroit · Oct 21, 2025
- Saline data center fight to arrive at Michigan Public Service Commission · Michigan Public · Dec 3, 2025
- MPSC approves DTE contracts to service Saline data center · WLNS · Dec 18, 2025
- How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · March 2, 2026
- A Michigan farm town voted down plans for a giant OpenAI-Oracle data center. Weeks later, construction began · Fortune · May 6, 2026
- The Barn Data Center (landuse=construction, industrial=data_centre) · OpenStreetMap · Oct 8, 2026
- OpenAI, Oracle, and Related Digital announce Stargate data center site in Michigan · Related Companies · Oct 30, 2025
- USGS aerial image of the site (older than the construction) · USGS The National Map · Oct 8, 2026
- EGLE takes comments on wastewater permit for onsite water treatment at Saline Township data center · Michigan Advance · Oct 22, 2026
- Michigan Data Centers: The Weekly Download · Michigan Advance · Nov 16, 2026
- Saline Township reaffirms tax break for massive data center project · The Detroit News · Nov 11, 2026
See something wrong? Tell us and we'll fix it.