Stargate data center campus ("The Barn"), Saline Township
Also called: The Barn, Stargate Michigan
OpenAI, Oracle and Related Digital are building a 1.4-gigawatt AI data center on about 250 acres of a 575-acre farm site in Saline Township. The township first said no, was sued, and then settled. The settlement bans water cooling, limits noise to 55 decibels and pays $14 million into local funds.
Where things stand: Under construction since late 2025 after a court settlement with the township and state approval of the power contracts.
๐ Latest update (Dec 18, 2025): MPSC approved DTE's power contracts with conditions, without a full contested case.
What we know
- ๐ WhereFarmland north of Michigan Avenue in Saline Township, Saline, Washtenaw County
- ๐ข CompanyRelated Digital
- ๐๏ธ Owned byRelated Companies
- ๐ค Built forOpenAI and Oracle
- ๐ณ Size250 acres
- โก Power it needs1,400 megawatts (about as much as 1,120,000 homes)
- ๐ Where the power comes fromDTE Energy; Oracle must add 1.4 gigawatts of battery storage within 15 years
- ๐ง Waterits own well and waste treatment, per the settlement
- โ๏ธ Coolingclosed-loop cooling; evaporative water cooling is not allowed under the court settlement
- ๐ต Cost$16 billion
- ๐ท Jobs promised450
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will the on-site well use per day? ๐ I'll find out
- Will new power lines or substations be built for the site? ๐ I'll find out
- Were any tax breaks given for the project? ๐ I'll find out
- Fortune reported about 475 more acres in nearby Bridgewater Township are part of the campus. What is planned there? ๐ I'll find out
What happened so far
- Sept 10, 2025Township board voted 4-1 to deny the rezoning.
- Sept 12, 2025Related Digital sued the township, calling the denial exclusionary zoning.
- Oct 15, 2025A settlement (consent judgment) was filed in Washtenaw County court, allowing the data center with conditions.
- Nov 2025Site work began weeks after the township's rejection vote.
- Dec 3, 2025State utility regulators (MPSC) held a public hearing on DTE's power contracts.
- Dec 18, 2025MPSC approved DTE's power contracts with conditions, without a full contested case.
Local votes and rules
โ๏ธ Court case
A judge refused a nearby resident's request to join the case and undo the Saline Township settlement. The judge said the request came too late and the board did approve the deal in a public vote. The resident's lawyer said they were looking at next steps.
๐ค Agreement with the company
The township settled the lawsuit and the data center was allowed. Terms: a 55-decibel noise limit, no water-based cooling, no expansion, about 200 acres kept as open land, plus $4 million for farmland, $2 million for a community fund and $8 million for fire services. A resident later asked the court to throw it out, saying the vote was not public.
โ๏ธ Court case
Developer Related Digital and the landowners sued Saline Township, saying the denial was 'exclusionary zoning'. The case ended with a consent judgment (a court-approved settlement) in October 2025.
โ Turned down
The township board voted 4-1 against rezoning farmland for a large data center. The developer sued two days later, and the township then settled (see the agreement record).
An aerial photo of the area.
Where this comes from
- Saline Township settles with data center developer: 'Lesser of two evils' ยท Planet Detroit ยท Oct 21, 2025
- Saline data center fight to arrive at Michigan Public Service Commission ยท Michigan Public ยท Dec 3, 2025
- MPSC approves DTE contracts to service Saline data center ยท WLNS ยท Dec 18, 2025
- How many AI data centers are planned in Michigan? We counted. ยท Gander Newsroom ยท March 2, 2026
- A Michigan farm town voted down plans for a giant OpenAI-Oracle data center. Weeks later, construction began ยท Fortune ยท May 6, 2026
See something wrong? Tell us and we'll fix it.