Send us a tip
Being builtBig (AI-size): 1,400 megawatts

Stargate data center campus ("The Barn"), Saline Township

Also called: The Barn, Stargate Michigan

OpenAI, Oracle and Related Digital are building a 1.4-gigawatt AI data center on about 250 acres of a 575-acre farm site in Saline Township. The township first said no, was sued, and then settled. The settlement bans water cooling, limits noise to 55 decibels and pays $14 million into local funds.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Board of Saline Township.

Where things stand: Being built Under construction since late 2025 after a court settlement with the township and state approval of the power contracts.

❓ 4 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 2026): Township trustees unanimously reaffirmed a 12-year, 50% tax break for the data center and moved to set up an Industrial Development District for it, despite residents' objections that legal steps were skipped.

What we know

  • 📍 WhereFarmland on the north side of Michigan Avenue (US-12) in Saline Township; entrance by the old red barn, Saline, Washtenaw County
  • 🏢 CompanyRelated Digital
  • 🏛️ Owned byRelated Companies
  • 👤 Built forOpenAI and Oracle
  • 🌳 Size250 acres
  • ⚡ Power it needs1,400 megawatts (about as much as 1,120,000 homes)
  • 🔌 Where the power comes fromDTE Energy; Oracle must add 1.4 gigawatts of battery storage within 15 years
  • 💧 Waterits own well and waste treatment, per the settlement
  • ❄️ Coolingclosed-loop cooling; evaporative water cooling is not allowed under the court settlement
  • 💵 Cost$16 billion
  • 👷 Jobs promised450

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the on-site well use per day? 🙋 I'll find out ·
  • Will new power lines or substations be built for the site? 🙋 I'll find out ·
  • Fortune reported about 475 more acres in nearby Bridgewater Township are part of the campus. What is planned there? 🙋 I'll find out ·
  • Will EGLE approve the permit to release treated sewage from the campus into the Saline River, and with what limits? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: OpenStreetMap maps 'The Barn Data Center' as a construction site of about 550 acres on the north side of Michigan Avenue in Saline Township. The pin is the middle of that area.

    What happened so far

    • Sept 10, 2025
      Township board voted 4-1 to deny the rezoning.
    • Sept 12, 2025
      Related Digital sued the township, calling the denial exclusionary zoning.
    • Oct 15, 2025
      A settlement (consent judgment) was filed in Washtenaw County court, allowing the data center with conditions.
    • Nov 2025
      Site work began weeks after the township's rejection vote.
    • Dec 3, 2025
      State utility regulators (MPSC) held a public hearing on DTE's power contracts.
    • Dec 18, 2025
      MPSC approved DTE's power contracts with conditions, without a full contested case.
    • Oct 21, 2026
      The state environment agency (EGLE) held a public hearing on a permit for an on-site plant that would clean the campus's sewage (from bathrooms and kitchens) and release it into the Saline River. Written comments closed Oct. 23. Cooling water is not covered and would be taken off site.
    • Nov 2026
      Township trustees unanimously reaffirmed a 12-year, 50% tax break for the data center and moved to set up an Industrial Development District for it, despite residents' objections that legal steps were skipped.

    Local votes and rules

    ⚖️ Court case

    A judge refused a nearby resident's request to join the case and undo the Saline Township settlement. The judge said the request came too late and the board did approve the deal in a public vote. The resident's lawyer said they were looking at next steps.

    Feb 20, 2026

    🤝 Agreement with the company

    The township settled the lawsuit and the data center was allowed. Terms: a 55-decibel noise limit, no water-based cooling, no expansion, about 200 acres kept as open land, plus $4 million for farmland, $2 million for a community fund and $8 million for fire services. A resident later asked the court to throw it out, saying the vote was not public.

    Oct 15, 2025

    ⚖️ Court case

    Developer Related Digital and the landowners sued Saline Township, saying the denial was 'exclusionary zoning'. The case ended with a consent judgment (a court-approved settlement) in October 2025.

    Sept 12, 2025

    ✋ Turned down

    The township board voted 4-1 against rezoning farmland for a large data center. The developer sued two days later, and the township then settled (see the agreement record).

    Sept 10, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something