USA › Indiana › Marion County

Marion County

5 data center projects we know about. 24 towns, townships and cities.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

Local votes and rules

⏸️ Pause on new data centers · Marion County

No new data centers can be approved in Marion County (Indianapolis) through December 31, 2027. The City-County Council voted 23-1 on August 10 and the Metropolitan Development Commission voted 6-0 on August 19. Three projects already approved are not affected.

Aug 19, 2026Source

✅ Approved · Decatur Township

The Metropolitan Development Commission approved tax breaks for the Sabey campus: a 10-year property tax break worth about $49.5 million and a 15-year equipment tax break worth about $36 million.

Aug 19, 2026Source

✅ Approved · Warren Township

The Metropolitan Development Commission voted 6-1 to approve a use variance for the DC Blox data center campus on the east side, the last local approval it needed. Opponents said they would go to court.

July 15, 2026Source

🗺️ Zoning change · Marion County

The Metropolitan Development Commission voted 5-3 to recommend a new zoning class with rules for data centers. It raised the noise limit back to 65 decibels and kept a 400-foot buffer from places like schools. The council then chose a pause while the rules are finished.

July 1, 2026Source

⚖️ Court case · Center Township

Martindale-Brightwood residents and the Hoosier Environmental Council went to court to stop the approved Metrobloks data center on a 14-acre former drive-in site. They ask the court to cancel the rezoning and block construction.

May 2026Source

⚖️ Court case · Decatur Township

Decatur Township residents asked the court to overturn the city's approval of Sabey's $4 billion data center and block construction. Sabey used a use variance instead of a rezoning, so the council could not call it up for a vote.

April 2026Source

📌 Other · Franklin Township

Most City-County Council members said they opposed Google's rezoning of about 468 acres in Franklin Township for a data center. Google withdrew the proposal in 2025.

Sept 2025Source