1 data center project in Warren Township
Who decides here: the Marion County Board of Commissioners usually decides on zoning in Warren Township. Townships here have little say over land use.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Metrobloks IND-A1 data center (Martindale-Brightwood)
Center Township, Marion County
14 acres
🕒 Aug 19, 2026: Indianapolis passed a data center pause through 2027. This project is exempt because it …
Stopped or cancelledabout 7 miles awayGoogle 'Project Flo' data center (Franklin Township, Indianapolis)
Franklin Township, Marion County
468 acres · for Google
🕒 Sept 22, 2025: Google withdrew its rezoning petition before the City-County Council could vote.
Stopped or cancelledabout 9 miles awayHancock County MegaSite data center proposal
Buck Creek Township, Hancock County
776 acres
🕒 May 2025: After a crowded public meeting, Surge withdrew the rezoning request.
Stopped or cancelledabout 13 miles awayAmerican Tower edge data center (Pike Township, Indianapolis)
Pike Township, Marion County
7 acres
🕒 Feb 2026: American Tower withdrew its rezoning request after pushback from neighbors.
Local votes and rules
⏸️ Pause on new data centers · Marion County
No new data centers can be approved in Marion County (Indianapolis) through December 31, 2027. The City-County Council voted 23-1 on August 10 and the Metropolitan Development Commission voted 6-0 on August 19. Three projects already approved are not affected.
✅ Approved
The Metropolitan Development Commission voted 6-1 to approve a use variance for the DC Blox data center campus on the east side, the last local approval it needed. Opponents said they would go to court.
🗺️ Zoning change · Marion County
The Metropolitan Development Commission voted 5-3 to recommend a new zoning class with rules for data centers. It raised the noise limit back to 65 decibels and kept a 400-foot buffer from places like schools. The council then chose a pause while the rules are finished.
What you can do
- Get told first.
We'll email you if anything changes in Warren Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Indianapolis Power & Light Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.
🙋 Open tasks here
- How many megawatts will the smaller two-building plan use?
- Will neighbors appeal the approval in court?
- Will the full City-County Council approve or reject the DC BLOX tax breaks in December 2026?