Send us a tip
Approved, not built yetBig (AI-size): 250 megawatts

Sabey Decatur Technology Park (Indianapolis)

Also called: Sabey Decatur Township Data Center

Sabey plans two large data center buildings (about 900,000 sq ft) and a substation on 130 acres in Decatur Township. It says it will invest up to $4 billion and reach 250 megawatts. The land was already zoned industrial, so the City-County Council did not need to vote. A local group, Protect Decatur Township, opposes it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Marion County Board of Commissioners (for Decatur Township).

Where things stand: Approved, not built yet Approved by the city development commission in March 2026; tax breaks approved in September 2026. Construction expected to start in 2027.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Sept 16, 2026): The city approved about $240 million in tax breaks for the project.

What we know

  • 📍 Where6400-6833 Kentucky Avenue and 6700-8210 Camby Road, southwest Decatur Township, Decatur Township, Marion County
  • 🏢 CompanySabey Data Center Properties LLC
  • 🏛️ Owned bySabey Data Centers
  • 🌳 Size130 acres
  • ⚡ Power it needs250 megawatts (about as much as 200,000 homes)
  • 🔌 Where the power comes fromAES Indiana. Sabey says it will pay for power upgrades.
  • ❄️ CoolingClosed-loop cooling (filled with about 1 million gallons of water, then topped up)
  • 💵 Cost$4 billion
  • 💸 Tax breaksAbout $240 million in tax breaks approved by the city in September 2026.
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many diesel backup generators will there be? 🙋 I'll find out ·
  • Will AES Indiana build new power lines, and who pays? 🙋 I'll find out ·
  • Did any official sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the city hearing agenda lists the parcel addresses on Kentucky Avenue and Camby Road; the pin is the middle of those parcels.

    What happened so far

    • March 18, 2026
      The Indianapolis Metropolitan Development Commission approved the data center campus.
    • Aug 19, 2026
      Indianapolis passed a data center pause through 2027. Sabey's already-approved project is exempt.
    • Sept 16, 2026
      The city approved about $240 million in tax breaks for the project.

    Local votes and rules

    ⏸️ Pause on new data centers

    No new data centers can be approved in Marion County (Indianapolis) through December 31, 2027. The City-County Council voted 23-1 on August 10 and the Metropolitan Development Commission voted 6-0 on August 19. Three projects already approved are not affected.

    Aug 19, 2026

    ✅ Approved

    The Metropolitan Development Commission approved tax breaks for the Sabey campus: a 10-year property tax break worth about $49.5 million and a 15-year equipment tax break worth about $36 million.

    Aug 19, 2026

    ⚖️ Court case

    Decatur Township residents asked the court to overturn the city's approval of Sabey's $4 billion data center and block construction. Sabey used a use variance instead of a rezoning, so the council could not call it up for a vote.

    April 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.