Sabey Decatur Technology Park (Indianapolis)
Also called: Sabey Decatur Township Data Center
Sabey plans two large data center buildings (about 900,000 sq ft) and a substation on 130 acres in Decatur Township. It says it will invest up to $4 billion and reach 250 megawatts. The land was already zoned industrial, so the City-County Council did not need to vote. A local group, Protect Decatur Township, opposes it.
Where things stand: Approved by the city development commission in March 2026; tax breaks approved in September 2026. Construction expected to start in 2027.
๐ Latest update (Sept 16, 2026): The city approved about $240 million in tax breaks for the project.
What we know
- ๐ WhereKentucky Avenue (State Road 67) and Camby Road, southwest Indianapolis, Decatur Township, Marion County
- ๐ข CompanySabey Data Center Properties LLC
- ๐๏ธ Owned bySabey Data Centers
- ๐ณ Size130 acres
- โก Power it needs250 megawatts (about as much as 200,000 homes)
- ๐ Where the power comes fromAES Indiana. Sabey says it will pay for power upgrades.
- โ๏ธ CoolingClosed-loop cooling (filled with about 1 million gallons of water, then topped up)
- ๐ต Cost$4 billion
- ๐ธ Tax breaksAbout $240 million in tax breaks approved by the city in September 2026.
- ๐ท Jobs promised100
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many diesel backup generators will there be? ๐ I'll find out
- Will AES Indiana build new power lines, and who pays? ๐ I'll find out
- Was a secret deal (NDA) signed with any official? ๐ I'll find out
What happened so far
- March 18, 2026The Indianapolis Metropolitan Development Commission approved the data center campus.
- Aug 19, 2026Indianapolis passed a data center pause through 2027. Sabey's already-approved project is exempt.
- Sept 16, 2026The city approved about $240 million in tax breaks for the project.
Drag the slider to compare the land before and now.
Where this comes from
- Indianapolis data centers, explained ยท Mirror Indy ยท 2026
- Indianapolis Metropolitan Development Commission approves Decatur Township data center proposal ยท FOX59
- Indianapolis data center moratorium receives final approval ยท Indianapolis Business Journal ยท Aug 19, 2026
See something wrong? Tell us and we'll fix it.