No project in Scipio Township, but 3 nearby
Who decides here: the LaPorte County Board of Commissioners usually decides on zoning in Scipio Township. Townships here have little say over land use.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Microsoft La Porte data center campus
La Porte, LaPorte County
1,300 acres · for Microsoft
🕒 June 17, 2026: Microsoft held a groundbreaking for the campus.
Approved, not built yetabout 11 miles awayGoogle Michigan City data center (Project Maize)
Michigan City, LaPorte County
70 acres · for Google
🕒 April 16, 2026: Google confirmed it is buying the Project Maize site.
Stopped or cancelledabout 13 miles awayAgincourt data center proposal, Valparaiso
Valparaiso, Porter County
180 acres
🕒 March 11, 2025: The mayor said Agincourt would withdraw and release its option on the land.
Local votes and rules
📜 Data center rules · LaPorte County
County commissioners voted unanimously for data center rules. Data centers are allowed only on industrial land, need approval from the zoning appeals board, and must meet setback and noise rules. It covers only the unincorporated county.
What you can do
- Get told first.
We'll email you if anything changes in Scipio Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Scipio Township: Northern Indiana Pub Serv Co. (company) or Kankakee Valley Rural E M C (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.