Being builtBig (AI-size): 1,300 acres

Microsoft La Porte data center campus

Also called: Radius Industrial Park

Microsoft is building a data center campus in La Porte. The first phase has six buildings, and plans grow to 17 buildings after the city annexed about 1,000 more acres. Microsoft says about 600 permanent jobs will come with the first phase.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of La Porte City.

Where things stand: Being built Groundbreaking was June 17, 2026. First three buildings expected done by 2029.

❓ 4 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (June 17, 2026): Microsoft held a groundbreaking for the campus.

What we know

  • 📍 WhereBetween Boyd Boulevard and County Road 250 South, near U.S. 35, south side of La Porte, La Porte, LaPorte County
  • 🏢 CompanyMicrosoft
  • 🏛️ Owned byMicrosoft
  • 👤 Built forMicrosoft
  • 🌳 Size1,300 acres
  • ❄️ CoolingClosed-loop liquid cooling (company claim)
  • 💵 Cost$1 billion
  • 💸 Tax breaksMicrosoft pays full property taxes; the city sends 15% of the tax money to La Porte schools for 20 years.
  • 👷 Jobs promised600

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the La Porte campus use? 🙋 I'll find out ·
  • How much water will it use, and from which utility? 🙋 I'll find out ·
  • How many diesel generators are planned? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news says Microsoft land stretches from Boyd Boulevard to County Road 250 South near U.S. 35. The pin is placed by hand in that area.

    What happened so far

    • June 2024
      Microsoft announced a $1 billion data center at Radius Industrial Park in La Porte.
    • May 2026
      La Porte Common Council approved rezoning for about 1,000 more acres for a second phase.
    • June 17, 2026
      Microsoft held a groundbreaking for the campus.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft breaks ground on La Porte data center · Inside Indiana Business · June 17, 2026
    2. Microsoft breaks ground on La Porte datacenter project · Microsoft · June 18, 2026
    3. Michiana Data Center Roundup · ABC57 · May 20, 2026
    4. La Porte Common Council approves expansion of Microsoft data center near Highway 35 · ABC57 · May 18, 2026
    5. Microsoft expands plans for La Porte, Indiana data center campus · DatacenterDynamics · April 2026
    6. LaPorte Common Council votes in favor of second Microsoft data center campus · WNDU 16 News Now · May 19, 2026
    7. Microsoft chooses La Porte as first Indiana data center location · Northwest Indiana Business Magazine · June 4, 2024