1 data center project in Forest Park City
Who decides here: the City Council of Forest Park City votes on zoning. The Clayton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
TA Realty data center (East Tanners Church Road)
Unincorporated Clayton County, Clayton County
🕒 June 2025: Development Authority of Clayton County approved a tax break for the $959 million project.
Reported in the news, not confirmed yet
Stopped or cancelledabout 4 miles awayEllenwood data center (PCC-DeKalb LLC)
Unincorporated DeKalb County, DeKalb County
95 acres
🕒 Aug 13, 2026: DeKalb County Board of Commissioners rejected the data center after almost a year of res…
Reported in the news, not confirmed yet
Stopped or cancelledabout 5 miles awayShadowbox Studios data center proposal
Unincorporated DeKalb County, DeKalb County
200 acres
🕒 Sept 9, 2026: DeKalb Zoning Board of Appeals affirmed the denial, leaving the matter to the courts.
Proposedabout 10 miles awayTA Realty ATL03 / Red Oak data center
Union City, Fulton County
67.8 acres
🕒 Oct 31, 2024: TA Realty filed four data center buildings (about 1 million square feet) for state regio…
Proposedabout 10 miles awayVantage data center (Stacks Road site, South Fulton)
South Fulton, Fulton County
🕒 Aug 13, 2024: Vantage filed a 697,000 square foot data center for state regional review (DRI #4257).
Proposedabout 11 miles awayThe Crossing Business Park data center campus (Union City)
Union City, Fulton County
232.15 acres
🕒 Oct 29, 2026: Union City filed The Crossing Business Park for state regional review (DRI #4825): a dat…
Proposedabout 12 miles awayATL11 data center (Stonewall Tell Road)
Union City, Fulton County
🕒 July 15, 2024: A 2.1 million square foot data center was filed for state regional review (DRI #4235).
Approved, not built yetabout 12 miles awayMicrosoft Union City data center campus (Stonewall Tell Road)
Union City, Fulton County
136 acres · for Microsoft
🕒 April 2024: Microsoft bought 136 acres in Fulton County for $53.5 million.
Reported in the news, not confirmed yet
Local votes and rules
⏸️ Pause on new data centers
Forest Park's city council approved a 90-day pause on data centers to write zoning changes. Data centers had been allowed by right, which let Digital Realty build there. The new rules would define data centers, set buffers from homes and add a community advisory committee.
What you can do
- Get told first.
We'll email you if anything changes in Forest Park City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Georgia Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Will it really use 3 million gallons of water a day, or less with a different cooling system?
- Was a tax break given?
- Has building construction started, and which permits has Forest Park issued?
- Has Georgia EPD approved the cleanup of the buried Army waste on the site?