Approved, not built yetBig (AI-size): 180 megawatts

TA Realty data center (East Tanners Church Road)

TA Realty plans a 180-megawatt data center worth about $959 million on East Tanners Church Road. County commissioners approved the site plan in 2024, and the county development authority gave it a 10-year tax break in 2025. The authority did not make the value of the tax break public.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Clayton County Board of Commissioners (for land outside city and town limits).

Where things stand: Approved, not built yet Site plan approved by county commissioners 3-1 in Oct. 2024; a 10-year tax break approved in June 2025.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 2025): Development Authority of Clayton County approved a tax break for the $959 million project.

What we know

  • 📍 Where4350 E Tanners Church Road, Ellenwood (about 35 acres, between Dunn and Williamson roads), Unincorporated Clayton County, Clayton County
  • 🏢 CompanySubsidiary of TA Realty
  • 🏛️ Owned byTA Realty
  • ⚡ Power it needs180 megawatts (about as much as 144,000 homes)
  • 💵 Cost$959 million
  • 💸 Tax breaksThe Development Authority of Clayton County approved a 10-year property tax break but would not say how much it is worth.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much property tax will the company save under the tax break? 🙋 I'll find out ·
  • How much water and power will it use? 🙋 I'll find out ·
  • Has construction started? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Oct 2024
      Clayton County Board of Commissioners approved the site plan 3-1 over resident opposition.
    • June 2025
      Development Authority of Clayton County approved a tax break for the $959 million project.

    Local votes and rules

    ⏸️ Pause on new data centers

    Clayton County commissioners voted for a 120-day pause on new data centers, through December 31, 2025, to study health, safety and water effects. News reports in 2026 still describe a Clayton County pause covering areas outside city limits; cities such as Lovejoy and Forest Park are not covered.

    Sept 3, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Clayton County agency approves tax break for $1B data center · The Atlanta Journal-Constitution · June 2025
    2. TA Realty: Ellenwood, ATL (4350 E Tanners Church Rd, 35 acres) · Baxtel · Oct 8, 2026