Projects
AWS Crossroads Technology Campus (Lee Hill District)
Spotsylvania County, Spotsylvania County
555 acres Β· for Amazon Web Services
π Sept 16, 2026: Planning Commission voted 4-2 to recommend approval.
Reported in the news, not confirmed yet
Approved, not built yetHunters Ridge South data center campus (Cosner Drive)
Spotsylvania County, Spotsylvania County
π Aug 26, 2025: Board of Supervisors approved the rezoning 5-2.
Reported in the news, not confirmed yet
Being builtPowerHouse 95 data center campus
Spotsylvania County, Spotsylvania County
145 acres
π Jan 2025: PowerHouse completed the purchase of 145 acres.
Reported in the news, not confirmed yet
ProposedAmazon's four Spotsylvania rezonings (about 2,000 acres)
Spotsylvania County, Spotsylvania County
2,000 acres Β· for Amazon Web Services
π June 2023: Amazon filed rezoning applications for nearly 2,000 acres.
Reported in the news, not confirmed yet
Local votes and rules
πΊοΈ Zoning change Β· Spotsylvania County
Supervisors voted 4-3 to require a special use permit for data centers, so they can no longer be built by right on industrial land. A similar motion had failed on a 3-3 tie in March 2025.