Approved, not built yet
Hunters Ridge South data center campus (Cosner Drive)
Supervisors approved a rezoning for up to 2.2 million square feet of data centers at the southern end of Cosner Drive.
Where things stand: Supervisors approved the rezoning 5-2 in August 2025.
π Latest update (Aug 26, 2025): Board of Supervisors approved the rezoning 5-2.
What we know
- π WhereSouthern end of Cosner Drive, Spotsylvania County, Spotsylvania County
- π’ CompanyHunters Ridge LLC
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the end user, and how big will it be in megawatts? π I'll find out
What happened so far
- Aug 26, 2025Board of Supervisors approved the rezoning 5-2.
Local votes and rules
πΊοΈ Zoning change
Supervisors voted 4-3 to require a special use permit for data centers, so they can no longer be built by right on industrial land. A similar motion had failed on a 3-3 tie in March 2025.
Feb 25, 2026
π°οΈ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Spotsylvania Board of Supervisors approve potential 2.2-million-square-foot data center campus Β· Fredericksburg Free Press Β· Aug 27, 2025