Send us a tip
Approved, not built yet

Hunters Ridge South data center campus (Cosner Drive)

Supervisors approved a rezoning for up to 2.2 million square feet of data centers at the southern end of Cosner Drive.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Spotsylvania County Board of Supervisors (for land outside city and town limits).

Where things stand: Approved, not built yet Supervisors approved the rezoning 5-2 in August 2025.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Aug 26, 2025): Board of Supervisors approved the rezoning 5-2.

What we know

  • 📍 WhereSouthern end of Cosner Drive, Spotsylvania County, Spotsylvania County
  • 🏢 CompanyHunters Ridge LLC

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the end user, and how big will it be in megawatts? 🙋 I'll find out ·
  • How many acres is the Hunters Ridge South site? The Planning Commission report said about 73 acres, but later reports say 127 acres. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 26, 2025
      Board of Supervisors approved the rezoning 5-2.

    Local votes and rules

    📌 Other

    Supervisors voted 4-2 for a resolution backing a state senator's call for the governor to pause new data centers statewide. It does not pause anything in the county by itself.

    Aug 11, 2026

    🗺️ Zoning change

    Supervisors voted 4-3 to require a special use permit for data centers, so they can no longer be built by right on industrial land. A similar motion had failed on a 3-3 tie in March 2025.

    Feb 25, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Spotsylvania Board of Supervisors approve potential 2.2-million-square-foot data center campus · Fredericksburg Free Press · Aug 27, 2025
    2. Spotsylvania Planning Commission recommends approval of 2.2 million square foot data center campus · Fredericksburg Free Press · Aug 11, 2025
    3. Hunters Ridge South · Baxtel