No project in Devine City, but 4 nearby
Who decides here: the City Council of Devine City votes on zoning. The Medina County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Rowan 'Project Cinco' data center campus (west of Lytle)
Unincorporated Medina County, Medina County
440 acres
🕒 April 28, 2025: Lytle City Council approved an 80% tax break, 5-0.
Proposedabout 14 miles awayTract 'Medina Technology Park' (U.S. 90 W and CR 4516, near Castroville)
Unincorporated Medina County, Medina County
265 acres
🕒 May 2026: Medina County residents spoke out against the planned technology park.
Reported in the news, not confirmed yet
Proposedabout 14 miles awayCyrusOne data center SAT14A (U.S. 90 West, near Castroville)
Unincorporated Medina County, Medina County
244 acres
🕒 July 2026: CyrusOne filed state plans for project SAT14A; Medina County created a tax zone for the …
Reported in the news, not confirmed yet
Being builtabout 15 miles awayMicrosoft data center campus SAT89-SAT91 (U.S. 90 West, near Castroville)
Unincorporated Medina County, Medina County
for Microsoft
🕒 March 2025: Microsoft filed state plans for two buildings (SAT89 and SAT90) at 2995 U.S. 90 West, co…
What you can do
- Get told first.
We'll email you if anything changes in Devine City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Devine City: Karnes Electric Co-op Inc. (co-op (owned by its members)) or AEP Texas Central Company (company) or Medina Electric Co-op, Inc. (co-op (owned by its members)) or Bandera Electric Co-op, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.