No project in Balch Springs City, but 7 nearby
Who decides here: the City Council of Balch Springs City votes on zoning. The Dallas County may review big projects too.
Nearby (within 15 miles)
QTS DFW2 campus (303 Mason Road)
unknown, Dallas County
π April 2025: QTS filed state plans for two buildings (470,000 and 560,000 sq ft) costing about $650 mβ¦
Reported in the news, not confirmed yet
Proposedabout 10 miles awayCrow Holdings / CleanArc data center campus (Stemmons Corridor, Dallas)
Dallas, Dallas County
40 acres
π Jan 20, 2026: Crow Holdings announced a 245 MW campus; first 70 MW building due late 2027.
Reported in the news, not confirmed yet
Being builtabout 12 miles awaySTACK Infrastructure DFW02 campus (Lancaster)
Lancaster, Dallas County
102 acres
Reported in the news, not confirmed yet
Proposedabout 12 miles awayYondr data center campus (Lancaster)
Lancaster, Dallas County
163 acres
Reported in the news, not confirmed yet
Approved, not built yetabout 13 miles awayProject Orange and Project Labrador data center campuses (Lancaster)
Lancaster, Dallas County
535 acres
π Aug 11, 2025: Lancaster City Council approved zoning and a development agreement for both sites.
Reported in the news, not confirmed yet
Being builtabout 14 miles awayPrime Data Centers Garland campus (4221 N. Garland Ave.)
Garland, Dallas County
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Balch Springs City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Balch Springs City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Trinity Valley Electric Co-op Inc. (co-op (owned by its members)) or Farmers Electric Co-op, Inc. (co-op (owned by its members)) or Hilco Electric Cooperative, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.