No project in McKinney City, but 3 nearby
Who decides here: the City Council of McKinney City votes on zoning. The Collin County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Aligned DFW-04 data center for Lambda (401 N. Star Road, Plano)
Plano, Collin County
44 acres · for Lambda (AI cloud company)
Reported in the news, not confirmed yet
Proposedabout 14 miles awayBT Aycock data center (CR 561, east of Princeton)
unknown, Collin County
50 acres
🕒 June 9, 2026: North Texas Groundwater Conservation District approved a water well for the data center.
Reported in the news, not confirmed yet
Stopped or cancelledabout 14 miles awayProject Tomahawk data center (Prosper, withdrawn)
Prosper, Denton County
37.3 acres
🕒 Sept 1, 2026: Prosper Planning and Zoning Commission voted 7-0 to recommend denial.
What you can do
- Get told first.
We'll email you if anything changes in McKinney City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in McKinney City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Farmers Electric Co-op, Inc. (co-op (owned by its members)) or Denton County Electric Co-op, Inc. (co-op (owned by its members)) or Grayson-collin Electric Co-op, Inc. (co-op (owned by its members)) or Fannin County Electric Co-op (not available).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.