Being built
Aligned DFW-04 data center for Lambda (401 N. Star Road, Plano)
Aligned is building a $700 million, 425,000 sq ft AI data center on 44 acres in Plano. AI cloud company Lambda will use it.
Where things stand: Under construction; due in 2026.
What we know
- ๐ Where401 N. Star Road, Plano, Collin County
- ๐ข CompanyAligned Data Centers
- ๐ค Built forLambda (AI cloud company)
- ๐ณ Size44 acres
- ๐ Where the power comes fromOwn on-site substation.
- โ๏ธ CoolingAir and liquid cooling
- ๐ต Cost$700 million
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power will it use? ๐ I'll find out
- How much water? ๐ I'll find out
- Did Plano give a tax break? ๐ I'll find out
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Aligned Partners With Lambda on $700M Data Center Project in Plano ยท REBusiness Online ยท May 8, 2025
See something wrong? Tell us and we'll fix it.