Being builtBig (AI-size): 1,400 megawatts

IREN Sweetwater 1 data center campus

Also called: Sweetwater 1, Sweetwater Hub

IREN is building a 1.4-gigawatt data center campus outside Sweetwater. Its substation was connected to the grid in 2026. With a second site, IREN plans a 2-gigawatt hub.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Nolan County Commissioners Court (for land outside city and town limits).

Where things stand: Being built The site's big substation was connected to the grid in spring 2026. Data center buildings are still being built.

❓ 4 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (May 2026): IREN connected the 1.4-gigawatt Sweetwater 1 substation to the ERCOT grid.

What we know

  • 📍 WhereOutside Sweetwater. Sources disagree on the county: some say Nolan County, one says Fisher County., Unincorporated Nolan County, Nolan County
  • 🏢 CompanyIREN Limited
  • 👤 Built forIREN AI cloud (customers not named for this site)
  • ⚡ Power it needs1,400 megawatts (about as much as 1,120,000 homes)
  • 🔌 Where the power comes fromTexas power grid (ERCOT); new high-voltage substation on site
  • 💸 Tax breaksThe Sweetwater Municipal Development District said local taxing bodies would decide any tax breaks; no details were public.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 2026
      IREN connected the 1.4-gigawatt Sweetwater 1 substation to the ERCOT grid.

    Local votes and rules

    🤝 Agreement with the company

    Nolan County commissioners approved a 10-year property tax break for a $7 billion, 200-megawatt Crusoe data center near Sweetwater. The deal includes more than $3 million a year in payments instead of taxes, more than $2 million a year in donations to the county, and limits on water use with well meters to protect the aquifer. The site will make its own power.

    April 13, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. IREN powers up initial phase of Sweetwater data center campus · Baxtel · May 6, 2026
    2. IREN announces plans to expand in Sweetwater with 2GW data center hub · KTAB / BigCountryHomepage · 2025