Approved, not built yetBig (AI-size): 830 acres

Compass Datacenters 830-acre campus (Red Oak)

Red Oak's City Council approved Compass Datacenters' plan for about 830 acres of data centers. It will be the sixth data center campus in the city. Many residents worry about noise, pollution and home values.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Red Oak City.

Where things stand: Approved, not built yet Red Oak City Council approved rezoning 4-1 in May 2026 despite a 2,200-signature petition.

❓ 4 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (June 2, 2026): Compass announced a $15 million grant for an animal shelter in Ellis County.

What we know

  • 📍 WhereRed Oak, Ellis County
  • 🏢 CompanyCompass Datacenters
  • 🌳 Size830 acres
  • 🔌 Where the power comes fromCompany says it pays for the grid upgrades it needs.
  • 💧 WaterCompany says it will use no city water for cooling.
  • 💸 Tax breaksCompass offered a $15 million grant to build an Ellis County animal shelter; county had not approved it as of June 2026.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 12, 2026
      City Council voted 4-1 near midnight to approve the 830-acre project after 150+ residents objected.
    • June 2, 2026
      Compass announced a $15 million grant for an animal shelter in Ellis County.

    Local votes and rules

    🗺️ Zoning change

    Red Oak City Council voted 4-1 to rezone 830 acres for a Compass Datacenters campus between Goodloe Lane, FM 2377, Pierce Road and Pratt Road. It is planned as eight two-story buildings worth about $9.45 billion. More than 130 opponents came to city meetings. Red Oak has given 10-year tax breaks to Google, Compass and DataBank.

    May 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?