Send us a tip
ProposedBig (AI-size): 120 megawatts

Soluna 'Project Hedy' crypto and AI data center (Cameron County)

Also called: Project Hedy

Soluna plans a 120-megawatt data center for bitcoin mining and AI next to a 200-megawatt wind farm in Cameron County, built in two phases. It still needs final power, land and grid approvals.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Cameron County Commissioners Court (for land outside city and town limits).

Where things stand: Proposed Power supply deal signed in April 2025; land and grid steps not finished.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (April 2025): Soluna signed a power supply agreement with a wind farm owner for Project Hedy.

What we know

  • 📍 WhereUnincorporated Cameron County, Cameron County
  • 🏢 CompanySoluna Holdings
  • ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
  • 🔌 Where the power comes fromNext to a 200 MW wind farm

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 2025
      Soluna signed a power supply agreement with a wind farm owner for Project Hedy.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Soluna secures wind supply deal for 120MW crypto data center in Texas · DatacenterDynamics · April 10, 2025
    2. Soluna Expands Wind-Powered Data Center Portfolio with Project Hedy · Data Center Knowledge · April 14, 2025

    See something wrong? Tell us and we'll fix it.