Soluna 'Project Hedy' crypto and AI data center (Cameron County)
Also called: Project Hedy
Soluna plans a 120-megawatt data center for bitcoin mining and AI next to a 200-megawatt wind farm in Cameron County, built in two phases. It still needs final power, land and grid approvals.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Cameron County Commissioners Court (for land outside city and town limits).
Where things stand: Proposed Power supply deal signed in April 2025; land and grid steps not finished.
❓ 2 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (April 2025): Soluna signed a power supply agreement with a wind farm owner for Project Hedy.
What we know
- 📍 WhereUnincorporated Cameron County, Cameron County
- 🏢 CompanySoluna Holdings
- ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
- 🔌 Where the power comes fromNext to a 200 MW wind farm
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Exactly where is the site? 🙋 I'll find out ·
- Has construction started? 🙋 I'll find out ·
What happened so far
- April 2025Soluna signed a power supply agreement with a wind farm owner for Project Hedy.
Drag the slider to compare the land before and now.
Where this comes from
- Soluna secures wind supply deal for 120MW crypto data center in Texas · DatacenterDynamics · April 10, 2025
- Soluna Expands Wind-Powered Data Center Portfolio with Project Hedy · Data Center Knowledge · April 14, 2025
See something wrong? Tell us and we'll fix it.