Soluna plans a 120-megawatt data center for bitcoin mining and AI next to a 200-megawatt wind farm in Cameron County, built in two phases. It still needs final power, land and grid approvals.
Where things stand: Power supply deal signed in April 2025; land and grid steps not finished.
๐ Latest update (April 2025): Soluna signed a power supply agreement with a wind farm owner for Project Hedy.
What we know
- ๐ WhereUnincorporated Cameron County, Cameron County
- ๐ข CompanySoluna Holdings
- โก Power it needs120 megawatts (about as much as 96,000 homes)
- ๐ Where the power comes fromNext to a 200 MW wind farm
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Exactly where is the site? ๐ I'll find out
- Has construction started? ๐ I'll find out
What happened so far
- April 2025Soluna signed a power supply agreement with a wind farm owner for Project Hedy.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Soluna secures wind supply deal for 120MW crypto data center in Texas ยท DatacenterDynamics ยท April 10, 2025
See something wrong? Tell us and we'll fix it.