Lancaster AI Hub / CoreWeave data center (Greenfield Road, Lancaster)
Also called: Lancaster East Data Center, Chirisa Technology Parks, Machine Investment Group, Lancaster AI Hub East, 216 Greenfield Road
CoreWeave plans an AI data center worth up to $6 billion at old printing plants in Lancaster, starting at 100 megawatts. The city signed the first public community benefits agreement for a data center: $20 million for the community, a water cap of 20,000 gallons a day, and noise limits.
Where things stand: City signed a community benefits agreement (CBA) in late 2025; a tracker lists the first site as under construction. A judge canceled a Sept. 2026 zoning hearing on a second Greenfield Road data center.
π Latest update (Sept 2026): A judge canceled a zoning hearing on the second Greenfield Road data center.
Lancaster City Planning Commission. We don't know yet if Lancaster AI Hub / CoreWeave data center (Greenfield Road, Lancaster) is on the agenda. Call the office to check before you go.
What we know
- π WhereFormer printing plant at 216 Greenfield Road (78 acres); a second former plant at 1375 Harrisburg Pike (66 acres) was also bought, Lancaster, Lancaster County
- π’ CompanyChirisa Technology Parks and Machine Investment Group
- π€ Built forCoreWeave (sole tenant)
- π³ Size144 acres
- β‘ Power it needs100 megawatts (about as much as 80,000 homes)
- π Where the power comes fromStarts at 100 MW, could grow to 300 MW; CBA requires 100% clean energy with penalties up to $10 million per building
- π§ WaterCity water, capped at 20,000 gallons per day per campus under the CBA Β· 20,000 gallons a day
- βοΈ CoolingClosed-loop cooling (CBA requirement)
- π΅ Cost$6 billion
- π· Jobs promised175
- π€ Secret deal (NDA)No
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- What is the status of the second Greenfield Road data center and why was its hearing canceled? π I'll find out
- How will the city enforce the CBA? π I'll find out
π What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits. The project's community benefits agreement caps water at 20,000 gallons a day per campus, which is the same as SRBC's threshold.
What happened so far
- 2025CoreWeave announced up to $6 billion for an AI data center in Lancaster (100 MW at first, up to 300 MW).
- 2025City and three developers signed a $20 million community benefits agreement; residents' group said the public was shut out of talks.
- Sept 2026A judge canceled a zoning hearing on the second Greenfield Road data center.
Local votes and rules
πΊοΈ Zoning change
After city staff let two data centers move forward as 'wholesale trade and storage,' Lancaster City Council voted in August 2025 to write data center zoning rules. Council then passed a change that limits future data centers to 16 parcels in suburban manufacturing zones, with a zoning hearing and noise, air quality and shutdown rules.
βοΈ Court case
A resident appealed the city's decision that two planned data centers, including a CoreWeave project on Greenfield Road, count as an allowed 'wholesale trade and storage' use. The developers then sued to challenge whether the appeal was valid, putting the zoning board hearing on hold.
Drag the slider to compare the land before and now.
Where this comes from
- CoreWeave plans $6bn data center in Lancaster, Pennsylvania Β· DatacenterDynamics Β· 2025
- Community benefit agreements for data center development Β· Federation of American Scientists
- Community benefits agreements for data centers Β· World Resources Institute
- Judge cancels Greenfield Road data center zoning hearing Β· LancasterOnline Β· Sept 2026
- Lancaster East Data Center (Greenfield Road) Β· More Than Just Parks Data Center Tracker Β· Sept 22, 2026
- PA DEP Data Center Permit Tracker Β· Pennsylvania DEP Β· Oct 6, 2026
- PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) Β· Pennsylvania DEP Β· Oct 6, 2026
- City of Lancaster home page - Featured Events Β· City of Lancaster Β· Oct 6, 2026
- Water Use by Data Centers in the Susquehanna River Basin - FAQ Β· Susquehanna River Basin Commission Β· 2026
- Water Application and Approval Viewer (WAAV) Β· Susquehanna River Basin Commission Β· Oct 6, 2026