Send us a tip
ProposedBig (AI-size): 450 megawatts

Prime Data Centers campus at Starpointe Business Park

Also called: Starpointe Data Center Campus, Rover-Fed

A Texas company wants to build seven data center buildings on about 120 acres at Starpointe Business Park in Hanover Township. It would make its own power with 105 gas engines. Township hearings are ongoing, and residents have raised worries about old gas wells under the site.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Wednesday, November 18, 2026, 6:00 PM Eastern Time (local time)

Hanover Township Board of Supervisors hearing

📍 Hanover Volunteer Fire Department, 9 Starck Drive, Burgettstown.

Continued Prime Data conditional use hearing, reported by the Observer-Reporter. Another session is set for Dec. 9. The township's own site did not list Nov. 18 yet when we checked.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

🗓️ Public hearing: Wednesday, December 9, 2026, 6:00 PM Eastern Time (local time)

Continued conditional use hearing on the Prime data center

How: Attend at the Hanover Volunteer Fire Department, 9 Starck Drive, Burgettstown.

👥 Reported, not confirmed yetSourceNot live: please check with the office first.

Where things stand: Proposed Conditional use hearings before Hanover Township supervisors began September 1, 2026 and are still going. DEP air permit for the on-site gas engines is pending.

❓ 8 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 12, 2026): Supervisors added more conditional use hearings for Nov. 18 and Dec. 9 after the developer said it has two more witnesses. The developer's lawyer said residents' cross-examination has taken more than 15 hours.

What we know

  • 📍 WhereStarpointe Business Park, a former strip mine, near Star Lake, Hanover, Washington County
  • 🏢 CompanyPrime Data Centers LLC (Dallas, Texas), with partner Generate Capital
  • 🌳 Size120 acres
  • ⚡ Power it needs450 megawatts (about as much as 360,000 homes)
  • 🔌 Where the power comes fromIts own gas power on site: 105 natural gas engines making 350-450 megawatts, plus batteries

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When is the next continued conditional use hearing, and when will supervisors vote? 🙋 I'll find out ·
  • How many old gas wells are under or near the site, and are they safe? 🙋 I'll find out ·
  • How much water will it use and from where? 🙋 I'll find out ·
  • When will DEP decide on the air permit for the 105 gas engines, and is there a public comment period? 🙋 I'll find out ·
  • Who is the tenant? 🙋 I'll find out ·
  • Did Hanover Township or the county sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Did the supervisors who went on the developer-paid trip report it on their yearly financial interest forms? 🙋 I'll find out ·
  • The Observer-Reporter now says the gas power plant would be 350 megawatts; earlier reports said 450. Which is right? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Nov 16, 2026: We checked the township website: it listed Prime Data hearings on Nov. 10 and 11, but no outcome.

    What happened so far

    • March 30, 2026
      Hanover Township passed an ordinance to regulate data centers (WTAE headline).
    • Aug 5, 2026
      Prime Data Centers proposed a seven-building complex at Starpointe; hundreds of residents came to a township meeting.
    • Sept 1, 2026
      Conditional use hearing began and ran more than three hours; more hearings were set for September and October.
    • Sept 23, 2026
      Engineer testified the campus would have 1.8 million square feet in seven buildings and 105 gas engines making 350-450 megawatts. An air permit application is pending at DEP.
    • Oct 1, 2026
      Residents' lawyers said up to 12 old gas wells may be on or near the site; the developer's engineer found one capped well. More study may be needed.
    • Oct 7, 2026
      At the continued hearing, Prime Data Centers' project lead testified the company paid for plane tickets and lunch for at least two of the three township supervisors on a July 2 visit to its data center campus near Chicago. She said the pending application was not discussed on the trip.
    • Nov 12, 2026
      Supervisors added more conditional use hearings for Nov. 18 and Dec. 9 after the developer said it has two more witnesses. The developer's lawyer said residents' cross-examination has taken more than 15 hours.

    Local votes and rules

    ✅ Approved

    Hanover Township supervisors are holding hearings on Prime Data Centers' request for a conditional use permit at Starpointe Business Park. The plan is a 350-450 megawatt, eight-building data center campus on about 120-126 acres of old strip-mine land, with its own natural gas power plant.

    Aug 5, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Engineer testifies on Starpointe data center power generation · Observer-Reporter · Sept 23, 2026
    2. Starpointe data center may need further study on nearby gas wells · Observer-Reporter · Oct 1, 2026
    3. Starpointe Data Center Campus (Rover-Fed) · More Than Just Parks Data Center Tracker
    4. PA DEP Data Center Permit Tracker · Pennsylvania DEP · Oct 6, 2026
    5. Starpointe data center hearing set for Monday · Observer-Reporter · Aug 31, 2026
    6. Starpointe data center developer paid for flights, lunch for township supervisors · Observer-Reporter · Oct 9, 2026
    7. Hanover Township home page (events) · Hanover Township, Washington County · Oct 19, 2026
    8. Starpointe data center hearings potentially nearing end · Observer-Reporter · Nov 2, 2026
    9. Starpointe data center hearings to continue into December · Observer-Reporter · Nov 12, 2026

    See something wrong? Tell us and we'll fix it.