1 data center project in South Strabane Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of South Strabane Township votes on zoning. The Washington County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In South Strabane Township
Local votes and rules
📜 Data center rules
South Strabane supervisors voted unanimously to adopt rules for data centers, plus a separate noise and dust law. Data centers must stay at least 1,500 feet from any lived-in home and sit on at least 30 acres.
June 10, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town
What you can do
- Get told first.
We'll email you if anything changes in South Strabane Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
FirstEnergy Pennsylvania (formerly West Penn Power) (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Has any data center company made an offer on the CNX land?
- Will the township pass a separate rule on gas power plants for data centers?
- Has CNX signed any agreement with a buyer or with local officials to keep the plans private (NDA)?