No project in Charleroi Borough, but 2 nearby
Who decides here: the Borough Council of Charleroi Borough votes on zoning. The Washington County Planning Commission usually reviews big projects too.
Nearby (within 15 miles)
Proposedabout 4 miles away
EQT option on former Wheeling-Pittsburgh Steel mill land (Mon River Industrial Park)
Allenport, Washington County
400 acres
🕒 Aug 14, 2026: Coal Center became the last of six towns (Stockdale, Roscoe, Dunlevy, Allenport, Elco, C…
Reported in the news, not confirmed yet
Proposedabout 10 miles awayElizabeth Township data center and gas plant proposal (former U.S. Steel landfill, 'Fiore Property')
Elizabeth, Allegheny County
549 acres
🕒 Oct 5, 2026: Public records showed plans for 11 to 28 two-story data center buildings (smallest optio…
Reported in the news, not confirmed yet
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled
What you can do
- Get told first.
We'll email you if anything changes in Charleroi Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
FirstEnergy Pennsylvania (formerly West Penn Power) (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.