Data center off Route 31 (South Huntingdon Township)
Also called: Stanton Farm data center
A company called TriEnergy wants to put a data center in a building of about 1 million square feet on farmland off Route 31, near I-70. The township says it cannot review the plans until the state approves a sewage permit. The plans do not say where the power would come from; a large gas power plant is about a mile away.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of South Huntingdon Township.
Where things stand: Proposed TriEnergy applied for a township land use permit in May 2026. The township says it cannot review plans until DEP approves a sewage permit. Early stage.
❓ 6 open questions about it: see below.
Last checked Oct 19, 2026.
🕒 Latest update (Sept 17, 2026): Township supervisors adopted a data center ordinance. Residents at the meeting strongly opposed any data center in the township.
What we know
- 📍 WhereOld farmland off Route 31, less than a mile from the Route 31 / I-70 interchange, just east of the Pittsburgh Renaissance Festival entrance (pin placed at the festival entrance road), South Huntingdon Township, Westmoreland County
- 🏢 CompanyTriEnergy Inc. (Sewickley); landowner Stanton Farm LLC
- 🌳 Size178 acres
- 🔌 Where the power comes fromNot stated in the filed plans. The site is about a mile from the Tenaska Westmoreland gas power plant (about 950 megawatts); the companies would not say if it would use that power.
- 💵 Cost$25 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where would the data center get its power? Would it use the nearby Tenaska gas plant? 🙋 I'll find out ·
- Has DEP approved the sewage permit for the site? 🙋 I'll find out ·
- How much water would it use per day? 🙋 I'll find out ·
- Who would use the data center? 🙋 I'll find out ·
- When will Westmoreland County review a site development plan? 🙋 I'll find out ·
- Did township officials sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
What happened so far
- Jan 2025The Westmoreland Conservation District approved a wastewater discharge permit for a warehouse on the site. The letter does not mention a data center.
- Oct 2025TriEnergy and the landowner signed a three-year agreement for the project.
- May 2026TriEnergy applied to the township for a land use permit for a $25 million data center in a building of about 1 million square feet.
- Sept 17, 2026Township supervisors adopted a data center ordinance. Residents at the meeting strongly opposed any data center in the township.
Local votes and rules
📜 Data center rules
South Huntingdon Township supervisors adopted a data center ordinance. Data centers must be set back 500 feet from property lines next to wooded areas with evergreen trees.
Drag the slider to compare the land before and now.
Where this comes from
- Data center proposed for South Huntingdon: 'Still in early stages' · TribLive (Tribune-Review) · Oct 13, 2026
- Developers Plan 1.1M Sq Ft Data Center Near SWPA Tenaska Gas Plant · Marcellus Drilling News · Oct 2026
See something wrong? Tell us and we'll fix it.