Send us a tip
USA › Pennsylvania › Mifflin County › Granville Township

1 data center project in Granville Township

Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Granville Township votes on zoning. The Mifflin County Planning Commission usually reviews big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Granville Township

🗓️ Next meeting of the people who decide: Jan 2027
Granville Township Zoning Hearing Board. We don't know yet if PA Data Center Partners project (Loop Road, Granville Township) is on the agenda. Call the office to check before you go.
Board expected to reconvene to deliberate and decide on the appeal.
📍 Date and place not announced yet.

Local votes and rules

📜 Data center rules · Mifflin County

Mifflin County commissioners approved Ordinance 2 of 2026, which sets rules for data center site planning, building and operations. It applies in towns covered by the county's subdivision and land development rules.

Aug 7, 2026Source

⚖️ Court case

Data center developers filed a challenge in county court against Granville Township's data center ordinance. The township solicitor said the developers want the first ordinance thrown out. The township is also considering changes to the ordinance.

Aug 2026Source

✋ Turned down

Granville Township supervisors rejected PA Data Center Partners' application for a data center on farmland along Loop Road. Officials said the application was missing a required traffic study certification and letters showing water and power would be available. The developer was told it could reapply.

July 20, 2026Source

📜 Data center rules

Granville Township passed zoning rules for data centers. They are allowed only in the Industrial zone with special approval, and must meet limits on noise, height, water use and lighting. In August 2026 the township began working on changes to the rules.

July 2026Source

📌 Other · Mifflin County

The Mifflin County Planning Commission released a guidance report on data centers. It explains power and water needs and says towns can use zoning to guide where data centers go, but cannot ban them completely.

May 28, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Granville Township.
  2. Go to township meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Granville Township. Nothing else.

⚡ Your electric company

FirstEnergy Pennsylvania (formerly Penelec) (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.

🙋 Open tasks here

  • What will the zoning hearing board decide on the developer's appeal?

How to help →