No project in Yatesville Borough, but 9 nearby
Who decides here: the Borough Council of Yatesville Borough votes on zoning. The Luzerne County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Plains Township data center site (KSR)
Plains Township, Luzerne County
🕒 Sept 22, 2026: Packed hearing on a 592-acre Energy and Technology Overlay District. Land purchases in t…
Reported in the news, not confirmed yet
Proposedabout 7 miles awayWilkes-Barre data center site (Avison Young)
Wilkes-Barre, Luzerne County
Reported in the news, not confirmed yet
Stopped or cancelledabout 8 miles awayMudiita data center campus idea (Ransom Township)
Ransom Township, Lackawanna County
530 acres
🕒 July 27, 2026: Owner said he does not plan a data center there right now; websites advertising an all-e…
Proposedabout 10 miles awayPopca LLC data center campus (Newton Township)
Newton Township, Lackawanna County
76 acres
🕒 Sept 18, 2026: The Times-Tribune listed the Newton project (2 buildings, 76 acres) as denied by the tow…
Proposedabout 11 miles awayScranton Materials data center campus (Ransom Township)
Ransom Township, Lackawanna County
251 acres
🕒 Sept 3, 2026: News reports said the developer's second lawsuit (asking a judge to rule on the zoning) …
Proposedabout 14 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…
Approved, not built yetabout 14 miles awayProject Gold (Clifton Township, Gouldsboro)
Clifton Township, Lackawanna County
1,000 acres
🕒 Aug 20, 2026: Judge ruled the township's old data center zoning law void; the settlement stays in effe…
Local votes and rules
🗺️ Zoning change · Luzerne County
Luzerne County is writing data center rules for the 19 towns that use county zoning. Every data center would need a special exception from the county zoning hearing board. The planning commission recommended it in May 2026 and meets Oct. 8 to review new changes from the county law office. County Council must still vote.
🗺️ Zoning change · Luzerne County
The Luzerne County Planning Commission sent the county's data center zoning rules to County Council and recommended adoption. Every data center would need a special exception from the county zoning hearing board. County Council has not set a vote date.
What you can do
- Get told first.
We'll email you if anything changes in Yatesville Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.