No project in Elverson Borough, but 6 nearby
Who decides here: the Borough Council of Elverson Borough votes on zoning. The Chester County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
'Boutique' data center (North Coventry Township)
North Coventry Township, Chester County
17 acres
🕒 Feb 23, 2026: Supervisors voted 3-2 to reject the sketch plan.
Reported in the news, not confirmed yet
Proposedabout 11 miles awayTitus Station AI data center campus (Cumru Township)
Cumru Township, Berks County
🕒 May 15, 2026: Developers announced plans; township had just passed a data center ordinance.
Stopped or cancelledabout 13 miles awayConstellation Energy data center (East Coventry Township, near Limerick nuclear plant)
East Coventry Township, Chester County
🕒 Feb 17, 2026: Constellation withdrew its application (BOS-25-002) for data center zoning changes; the …
Proposedabout 14 miles awayPublicker site data center (1301 Main St., Linfield, Limerick Township)
Limerick Township, Montgomery County
191.46 acres
🕒 Sept 2026: Township agreed to the developer's request to delay hearings. The extension runs to Jan.…
Proposedabout 15 miles awayProject Laurel (MCD 7 LLC, Limerick Township)
Limerick Township, Montgomery County
192 acres · for Not named (developer cites NDAs)
🕒 April 2026: Township planners asked for new will-serve letters from Pennsylvania American Water to s…
Proposedabout 15 miles awayPennhurst data center (East Vincent Township)
East Vincent Township, Chester County
125 acres
🕒 June 26, 2026: Penn Hurst Holdings DE LLC appealed the denial to the Chester County Court of Common Ple…
Local votes and rules
📌 Other · Chester County
The Chester County Planning Commission, working with Montgomery County, published a Data Center Ordinance Guide with sample zoning rules towns can copy. It suggests allowing large data centers only through a conditional use review, keeping them 1,000 feet from homes, and limiting height and noise.
What you can do
- Get told first.
We'll email you if anything changes in Elverson Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.