📣 Report Something
USA › Mississippi › Hinds County › Clinton City

1 data center project in Clinton City

Who decides here: the City Council of Clinton City votes on zoning. The Hinds County may review big projects too.

In Clinton City

Nearby (within 15 miles)

Local votes and rules

📜 Data center rules

Aldermen voted unanimously to define data centers in the zoning code, including crypto mining and AI centers. New data centers need a conditional use permit and are only allowed in the I-1 and I-2 industrial zones.

June 2, 2026Source

✅ Approved

Aldermen approved a conditional use permit, a size variance and a deal to pay a set fee instead of regular property taxes (fee in lieu) for a $750 million data center in the former Delphi building at 1001 Industrial Park Drive. The company was not named at first; Amazon later said it will retrofit the building.

March 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Clinton City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Clinton City. Nothing else.

⚡ Your electric company

Entergy Mississippi LLC (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Mississippi.

🙋 Open tasks here

  • How much power will the Clinton data center use?
  • How many diesel backup generators will it have?
  • When will it open?

How to help →