Approved, not built yet

Amazon data center in the former Delphi plant in Clinton

Also called: AWS Clinton data center, 1001 Industrial Park Drive

Amazon plans to turn the empty former Delphi factory in Clinton into a data center, a $1 billion project with about 100 jobs. Clinton approved the zoning and a tax deal in 2026. Amazon says this site will not use water for cooling.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Clinton aldermen approved a conditional use, a variance and a fee-in-lieu deal in early 2026; Amazon confirmed the $1 billion project in April 2026.

๐Ÿ•’ Latest update (April 9, 2026): Gov. Reeves announced Amazon will spend $1 billion to retrofit the former Delphi building in Clinton, with 100 jobs.

What we know

  • ๐Ÿ“ WhereFormer Delphi plant, 1001 Industrial Park Drive, Clinton, Hinds County
  • ๐Ÿข CompanyAmazon Web Services
  • ๐Ÿ›๏ธ Owned byAmazon
  • ๐Ÿ‘ค Built forAmazon Web Services
  • ๐Ÿ”Œ Where the power comes fromEntergy Mississippi
  • โ„๏ธ CoolingAmazon says the Clinton site will not use water for cooling.
  • ๐Ÿ’ต Cost$1 billion
  • ๐Ÿ’ธ Tax breaksFee-in-lieu-of-taxes deal approved by the Clinton Board of Aldermen.
  • ๐Ÿ‘ท Jobs promised100

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • March 2026
    Clinton Board of Aldermen approved a conditional use, a variance and a fee-in-lieu-of-taxes deal for a $750 million data center in the 730,000 sq ft former Delphi building. AWS said it supported the project.
  • April 9, 2026
    Gov. Reeves announced Amazon will spend $1 billion to retrofit the former Delphi building in Clinton, with 100 jobs.

Local votes and rules

๐Ÿ“œ Data center rules

Aldermen voted unanimously to define data centers in the zoning code, including crypto mining and AI centers. New data centers need a conditional use permit and are only allowed in the I-1 and I-2 industrial zones.

June 2, 2026

โœ… Approved

Aldermen approved a conditional use permit, a size variance and a deal to pay a set fee instead of regular property taxes (fee in lieu) for a $750 million data center in the former Delphi building at 1001 Industrial Park Drive. The company was not named at first; Amazon later said it will retrofit the building.

March 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. AWS supports proposed $750 million Clinton, MS, AI data center project ยท Clarion Ledger (via Yahoo News) ยท March 5, 2026
  2. Amazon continues Mississippi expansion, announcing plans to invest a total of $25 billion across the Magnolia State ยท Office of Governor Tate Reeves ยท April 9, 2026
  3. Amazon is expanding data centers in central Mississippi, governor announces ยท Mississippi Free Press ยท April 9, 2026

See something wrong? Tell us and we'll fix it.