No project in Woodbury City, but 4 nearby
Who decides here: the City Council of Woodbury City votes on zoning. The Washington County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
QLevr data center at former Travel Tags site (Inver Grove Heights)
Inver Grove Heights, Dakota County
🕒 Sept 14, 2026: City Council voted 3-1 to exempt the QLevr project from the moratorium, settling the law…
Being builtabout 11 miles awayOppidan data center on Argenta Trail (Eagan)
Eagan, Dakota County
14.51 acres
🕒 June 2025: Oppidan broke ground on a 61,000 square foot data center, built for one tenant.
Reported in the news, not confirmed yet
Proposedabout 12 miles awayDakota East Area site in Rosemount (Tract technology park plan)
Rosemount, Dakota County
447 acres
🕒 July 15, 2025: Rosemount adopted the environmental review (AUAR) as adequate.
Reported in the news, not confirmed yet
Being builtabout 14 miles awayMeta Rosemount data center
Rosemount, Dakota County
280 acres · for Meta
🕒 March 14, 2024: Meta and Gov. Walz announced an $800 million, 715,000 square foot data center in Rosemou…
What you can do
- Get told first.
We'll email you if anything changes in Woodbury City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Woodbury City: Northern States Power Co. - Minnesota (company) or City of St Paul (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Minnesota.