1 data center project in Gibraltar City
Who decides here: the City Council of Gibraltar City votes on zoning. The Wayne County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Solstice Data center, Enterprise Drive, Allen Park
Allen Park, Wayne County
🕒 June 4, 2026: Planning commission voted 7-2 to deny the site plan and asked the city to pause data cen…
Stopped or cancelledabout 14 miles awayWarehouse data center conversion, Southern Street, Inkster
Inkster, Wayne County
🕒 Oct 19, 2026: At a packed meeting, no city council member moved to approve the permit, so it was never…
Being builtabout 15 miles awayGoogle data center (Project Cannoli), Van Buren Township
Van Buren Township, Wayne County
282 acres · for Google
🕒 Oct 30, 2026: Michigan Attorney General Dana Nessel asked state utility regulators (MPSC) to rehear th…
Local votes and rules
🤝 Agreement with the company · Wayne County
The Wayne County Commission voted 13-0 to override County Executive Warren Evans's Sept. 25 veto of tax breaks for the Google data center in Van Buren Township.
⚖️ Court case
Raeden and Cal Realty sued Gibraltar in federal court. They say their application for a 100-megawatt data center at 27800 W. Jefferson Ave. came before the pause and must be reviewed under the old rules.
⏸️ Pause on new data centers
Gibraltar passed a one-year pause on data centers, after a developer had already applied to build one on the old McLouth Steel site.
What you can do
- Get told first.
We'll email you if anything changes in Gibraltar City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Gibraltar City: Wyandotte Municipal Serv Comm (run by the town) or DTE Electric Company (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Michigan.
🙋 Open tasks here
- Has the federal court ruled on Raeden's lawsuit?
- Who would use the data center?