2 data center projects in De Soto City

Who decides here: the City Council of De Soto City votes on zoning. The Johnson County may review big projects too.

In De Soto City

Nearby (within 15 miles)

Local votes and rules

βœ… Approved

The planning commission approved Digital Realty's Phase One site plan, one two-story building. Later phases still need city approval.

Sept 22, 2026Source

πŸ“Œ Other

Residents started a petition to block 'high-impact' data centers by putting the question to a city vote. It could affect later phases of the Digital Realty campus.

Sept 2026Source

βœ… Approved

City council approved early plans for Beale Infrastructure's data center campus (four buildings). In April 2026 the planning commission approved a larger plan.

Aug 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in De Soto City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in De Soto City. Nothing else.

⚑ Your electric company

Depending on where you live in De Soto City: Evergy Kansas Central, Inc. (company) or Evergy Metro (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Kansas.

πŸ™‹ Open tasks here

  • How many megawatts will the Beale De Soto campus use?
  • Who is the end user?
  • Which utility will supply power, and are new power lines needed?
  • How many megawatts will the Digital Realty De Soto campus use?
  • Will Digital Realty get tax increment financing (TIF), and how much?
  • How big will the full campus be?