Red Wolf data center campus west of Kansas Speedway
Also called: Project Red Wolf, Red Wolf DCD Properties
A developer wants to build six big data center buildings on about 548 acres west of Kansas Speedway in Kansas City, Kansas. It would cost about $12.6 billion and use up to 600 megawatts of power. The company that would use it has not been named. Neighbors filed a protest petition and a lawsuit, and the project has stalled.
Where things stand: Rezoning partly passed in 2025, but the north half failed a needed supermajority vote and residents sued. No final deal with the city utility as of January 2026.
π Latest update (Jan 29, 2026): Reported still in early planning, with no signed deal with BPU or the Unified Government.
What we know
- π WhereBoth sides of Parallel Parkway, several miles west of Kansas Speedway, western Wyandotte County (Piper school district), Kansas City, Wyandotte County
- π’ CompanyRed Wolf DCD Properties LLC
- π³ Size548 acres
- β‘ Power it needs600 megawatts (about as much as 480,000 homes)
- π Where the power comes fromKansas City Board of Public Utilities (BPU) grid; developer agreed to pay for two new substations. 600 MW is more than BPU's whole current system (about 500 MW).
- π΅ Cost$12.6 billion
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the end user of the Red Wolf data center? π I'll find out
- What happened in the residents' lawsuit against the Unified Government over the rezoning? π I'll find out
- Is the north half of the site rezoned or not? π I'll find out
- How much water would the campus use per day? π I'll find out
What happened so far
- May 2025Unified Government planning commission voted 4-2 to recommend rezoning about 550 acres for six large data center buildings.
- July 31, 2025Rezoning of the north side got a 7-3 vote, short of the supermajority required after neighbors filed a protest petition.
- Oct 29, 2025A district judge refused to dismiss residents' lawsuit over the south side rezoning.
- Jan 29, 2026Reported still in early planning, with no signed deal with BPU or the Unified Government.
Local votes and rules
βοΈ Court case
Residents sued over the rezoning of the south part of the Red Wolf site. A judge refused to dismiss the case in October 2025. We found no final ruling.
πΊοΈ Zoning change
The planning commission recommended rezoning about 550 acres 4-2 in May 2025. The board's 7-3 vote on the north part fell short of the supermajority needed after neighbors filed a protest petition.
An aerial photo of the area.
Where this comes from
- Kansas City, Kansas, planning commission advances proposed $12.6B data center Β· Kansas Reflector via Route Fifty Β· May 30, 2025
- Lawsuit delays $12 billion Kansas City, Kansas, data center after community concerns Β· Kansas Reflector via HPPR Β· Nov 10, 2025
- Wyandotte County data centers would require a lot of power. Will that raise your energy bill? Β· The Beacon via KCUR Β· Jan 29, 2026