No project in German Township, but 2 nearby
Who decides here: the St. Joseph County Board of Commissioners usually decides on zoning in German Township. Townships here have little say over land use.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Amazon (AWS) New Carlisle data center campus
St. Joseph County
1,200 acres · for Amazon Web Services (AI work for Anthropic)
🕒 Oct 2025: Amazon switched on the campus ("Project Rainier"), with about 500,000 AI chips.
Proposedabout 10 miles awayMicrosoft Granger data center
St. Joseph County
930 acres · for Microsoft
🕒 Nov 12, 2026: The St. Joseph County Board of Zoning Appeals approved Microsoft's request for a 30-foot…
Local votes and rules
🚫 Ban · St. Joseph County
The county council voted 6-3 to ask the Area Plan Commission to change zoning to ban new hyperscale data centers. It is expected back for a final vote within 60 days.
✋ Turned down · St. Joseph County
After an eight-hour meeting, the county council voted 7-2 against rezoning more than 1,000 acres of farmland near New Carlisle for a $12 billion data center campus.
What you can do
- Get told first.
We'll email you if anything changes in German Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Indiana Michigan Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.