Proposed
Microsoft Granger data center
Microsoft bought about 930 acres of farmland in Granger to build a data center. The project was delayed by a debate over who would provide water and sewer. In March 2026 the county approved an early planning deal; residents raised worries about flooding, noise and generators.
Where things stand: Microsoft owns the land. In March 2026 the county approved an early planning deal (MOU). Construction was expected to start in fall 2026.
๐ Latest update (March 17, 2026): The St. Joseph County Redevelopment Commission approved an early planning agreement (MOU) with Microsoft and Mishawaka.
What we know
- ๐ WhereFarmland near Cleveland Road in Granger, St. Joseph County
- ๐ข CompanyMicrosoft
- ๐๏ธ Owned byMicrosoft
- ๐ค Built forMicrosoft
- ๐ณ Size930 acres
- ๐ง WaterCity of Mishawaka (water and sewer), per local reports
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many buildings and megawatts will the Granger campus have? ๐ I'll find out
- How much water will it use per day? ๐ I'll find out
- How many diesel generators will be on site? ๐ I'll find out
- Which township is the site in? ๐ I'll find out
What happened so far
- June 2024Microsoft bought nearly 930 acres of farmland in Granger for $77.5 million.
- March 17, 2026The St. Joseph County Redevelopment Commission approved an early planning agreement (MOU) with Microsoft and Mishawaka.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- Plans progressing for Microsoft's northern Indiana data centers ยท Inside Indiana Business ยท 2025
- Microsoft data center MOU approved in St. Joseph County amid resident concerns ยท WNDU ยท March 17, 2026
- Michiana Data Center Roundup ยท ABC57 ยท May 20, 2026