Microsoft Granger data center
Microsoft bought about 930 acres of farmland in Granger to build a data center. The project was delayed by a debate over who would provide water and sewer. In March 2026 the county approved an early planning deal; residents raised worries about flooding, noise and generators.
What happens next?
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Microsoft owns the land. In March 2026 the county approved an early planning deal (MOU). Construction was expected to start in fall 2026.
❓ 5 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Nov 12, 2026): The St. Joseph County Board of Zoning Appeals approved Microsoft's request for a 30-foot sound wall near the data center, along the Indiana Toll Road. Construction is underway.
What we know
- 📍 WhereFarmland northwest of Bittersweet and Cleveland roads, near Currant Road, Granger, St. Joseph County
- 🏢 CompanyMicrosoft
- 🏛️ Owned byMicrosoft
- 👤 Built forMicrosoft
- 🌳 Size930 acres
- 💧 WaterCity of Mishawaka (water and sewer), per local reports
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many buildings and megawatts will the Granger campus have? 🙋 I'll find out ·
- How much water will it use per day? 🙋 I'll find out ·
- How many diesel generators will be on site? 🙋 I'll find out ·
- Which township is the site in? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: news says the land is northwest of Bittersweet and Cleveland roads, near Currant Road. The pin is placed by hand inside that area.
What happened so far
- June 2024Microsoft bought nearly 930 acres of farmland in Granger for $77.5 million.
- March 17, 2026The St. Joseph County Redevelopment Commission approved an early planning agreement (MOU) with Microsoft and Mishawaka.
- Nov 12, 2026The St. Joseph County Board of Zoning Appeals approved Microsoft's request for a 30-foot sound wall near the data center, along the Indiana Toll Road. Construction is underway.
Drag the slider to compare the land before and now.
Where this comes from
- Plans progressing for Microsoft's northern Indiana data centers · Inside Indiana Business · 2025
- Microsoft data center MOU approved in St. Joseph County amid resident concerns · WNDU · March 17, 2026
- Michiana Data Center Roundup · ABC57 · May 20, 2026
- Microsoft, latest tech giant coming to St. Joseph County, officially buys 900 acres in Granger · WVPE · June 4, 2024
- Microsoft acquires land in Granger for data center (near Currant and Cleveland roads) · Inside INdiana Business · June 2024
- St. Joseph County board approves sound wall around Microsoft data center · WNDU · Nov 12, 2026
- 30 foot data center sound wall approved by St. Joseph County Board of Zoning Appeals · 95.3 MNC · Nov 13, 2026
See something wrong? Tell us and we'll fix it.