ProposedBig (AI-size): 930 acres

Microsoft Granger data center

Microsoft bought about 930 acres of farmland in Granger to build a data center. The project was delayed by a debate over who would provide water and sewer. In March 2026 the county approved an early planning deal; residents raised worries about flooding, noise and generators.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Proposed Microsoft owns the land. In March 2026 the county approved an early planning deal (MOU). Construction was expected to start in fall 2026.

❓ 5 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Nov 12, 2026): The St. Joseph County Board of Zoning Appeals approved Microsoft's request for a 30-foot sound wall near the data center, along the Indiana Toll Road. Construction is underway.

What we know

  • 📍 WhereFarmland northwest of Bittersweet and Cleveland roads, near Currant Road, Granger, St. Joseph County
  • 🏢 CompanyMicrosoft
  • 🏛️ Owned byMicrosoft
  • 👤 Built forMicrosoft
  • 🌳 Size930 acres
  • 💧 WaterCity of Mishawaka (water and sewer), per local reports

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many buildings and megawatts will the Granger campus have? 🙋 I'll find out ·
  • How much water will it use per day? 🙋 I'll find out ·
  • How many diesel generators will be on site? 🙋 I'll find out ·
  • Which township is the site in? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news says the land is northwest of Bittersweet and Cleveland roads, near Currant Road. The pin is placed by hand inside that area.

    What happened so far

    • June 2024
      Microsoft bought nearly 930 acres of farmland in Granger for $77.5 million.
    • March 17, 2026
      The St. Joseph County Redevelopment Commission approved an early planning agreement (MOU) with Microsoft and Mishawaka.
    • Nov 12, 2026
      The St. Joseph County Board of Zoning Appeals approved Microsoft's request for a 30-foot sound wall near the data center, along the Indiana Toll Road. Construction is underway.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something