No project in Berwyn City, but 7 nearby
Who decides here: the City Council of Berwyn City votes on zoning. The Cook County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Data center conversion at 300 West Adams Street (Chicago Loop)
Chicago, Cook County
🕒 Aug 6, 2026: The Permit Review Committee of the Chicago Landmarks Commission approved the plan. The f…
Reported in the news, not confirmed yet
Being builtabout 9 miles awayHydraVault AI data center (2538 S. Wabash Ave., Chicago)
Chicago, Cook County
🕒 Oct 28, 2025: HydraVault said it got a construction permit and began work.
Reported in the news, not confirmed yet
Being builtabout 13 miles awayCyrusOne data center campus (Bryn Mawr Avenue, Wood Dale)
Wood Dale, DuPage County
62 acres
🕒 May 2025: CyrusOne finished the frame of the first 18-megawatt building.
Reported in the news, not confirmed yet
Being builtabout 13 miles awayTA Realty ORD01 data center (Elmhurst and Old Higgins roads)
Elk Grove Village, Cook County
47 acres
🕒 Oct 3, 2025: Demolition was underway to make way for the 47-acre data center campus.
Reported in the news, not confirmed yet
Approved, not built yetabout 14 miles awayStream Data Centers campus (Landmeier Road area, Elk Grove Village)
Elk Grove Village, Cook County
34 acres
🕒 2025: ComEd broke ground on a 260-megawatt substation for the Stream campus.
Reported in the news, not confirmed yet
Stopped or cancelledabout 15 miles awayCloud Centers data center at former Lockformer site (711 Ogden Ave., Lisle)
Lisle, DuPage County
18 acres
🕒 March 2026: Developer told the village it withdrew its application.
Status unclearabout 15 miles awayRelated Digital data center at former U.S. Steel South Works (Chicago)
Chicago, Cook County
🕒 Aug 2026: Residents protested the neighboring quantum park, fearing a data center; Related Midwest…
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Berwyn City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Commonwealth Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.