Status unclearBig (AI-size): 1,000 megawatts

Related Digital data center at former U.S. Steel South Works (Chicago)

Related announced a huge 1,000-megawatt data center next to the planned Illinois Quantum and Microelectronics Park on Chicago's South Side. The developer now says a data center is not part of the first phase. Neighbors remain worried.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Chicago City.

Where things stand: Status unclear Related announced a 1-gigawatt data center in March 2025. In 2026 its developer said a data center is not part of the first phase of the quantum park. Plans are unclear.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 2026): Residents protested the neighboring quantum park, fearing a data center; Related Midwest said a data center is not part of the first phase.

What we know

  • 📍 Where8080 S. DuSable Lake Shore Drive (north part of the former South Works site, South Chicago), Chicago, Cook County
  • 🏢 CompanyRelated Digital (Related Midwest)
  • ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the 1-gigawatt data center at South Works still planned? 🙋 I'll find out ·
  • If it is built, how much water and power would it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the address 8080 S. Lake Shore Drive was found on the map at the north part of the former South Works site.

    What happened so far

    • March 2025
      Related announced a 1-gigawatt data center for the north side of the 440-acre South Works site.
    • Aug 2026
      Residents protested the neighboring quantum park, fearing a data center; Related Midwest said a data center is not part of the first phase.

    Local votes and rules

    ⏸️ Pause on new data centers

    The mayor and three aldermen introduced an ordinance for a 12-month pause on new data centers in Chicago. The City Council has not voted on it. The same day, the council passed a rule that data centers must report their yearly water and energy use.

    Sept 23, 2026

    📌 Other

    Mayor signed Executive Order 2026-5. It adds a review of power, water, backup generators, air pollution and noise for new data centers, and asks the city council to pass a temporary pause. Air and noise rules are due about November 9, 2026; a task force reports by March 15, 2027.

    Aug 11, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Inside the Pritzkers' 'Quantum Prairie' · Chicago Reader · 2026
    2. Data centers are popping up all over Chicago. Here's where — and why they're controversial · Block Club Chicago · Aug 12, 2026
    3. Locals rally against Chicago quantum park; company commits to no data center · Associated Press (via News-Shield) · Aug 2026
    4. Geocode of 8080 S. Lake Shore Drive, Chicago · Photon (OpenStreetMap) · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.