Meta Kuna data center
Kuna, Ada County
485 acres Β· for Meta
π Sept 3, 2026: Meta said the data center is open and fully running. It said it invested $1.2 billion.
Approved, not built yetGemstone Technology Park data center campus
Kuna, Ada County
620 acres Β· for unknown (an unnamed data center client)
π April 1, 2025: Kuna City Council approved the land-use change and rezoning 3-2, with the mayor breakingβ¦
Nearby (within 15 miles)
ValorC3 Boise data center on Emerald Street
Boise, Ada County
for A large tech company (not named)
π April 2026: ValorC3 closed a loan to keep building, backed by a long lease with a big tech company.
Proposedabout 10 miles awayRhea Data center and gas power plant near Blacks Creek Reservoir
Unincorporated Ada County, Ada County
3,750 acres
π Sept 21, 2026: BLM said it plans a notice in the Federal Register before the end of 2026, which opens pβ¦
Approved, not built yetabout 10 miles awayT5 data center in an existing Nampa building
Nampa, Canyon County
7.6 acres Β· for One user (not named)
π Aug 26, 2025: Nampa Planning and Zoning Commission heard and approved the conditional use permit CUP-0β¦
Local votes and rules
πΊοΈ Zoning change
The city council voted 3-2, with the mayor breaking a tie, to change about 620 acres of farmland in southeast Kuna to industrial use for Diode Ventures' Gemstone Technology Park data center campus.
What you can do
- Get told first.
We'll email you if anything changes in Kuna City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Idaho Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Idaho.
π Open tasks here
- How much electricity does the Kuna data center use at full load?
- How much water does it use in the hottest months?
- Did Meta get Idaho's data center sales tax break, and how much is it worth?
- Who will use the data centers?
- How much power will the campus use?
- Has the design review been filed or approved?
- Has the state approved the change of its water rights to industrial use?