Built & running

Meta Kuna data center

Also called: Brisbie, LLC, Kuna Data Center

Meta's first Idaho data center, in Kuna south of Boise. It is now open. It was first planned at $800 million but was redesigned for AI and grew to $1.2 billion. Regulators expect it to be Idaho Power's largest single customer.

βœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: Open and serving Meta's apps since about September 2026.

πŸ•’ Latest update (Sept 3, 2026): Meta said the data center is open and fully running. It said it invested $1.2 billion.

What we know

  • πŸ“ WhereSoutheast Kuna, near Pleasant Valley, in open desert, Kuna, Ada County
  • 🏒 CompanyMeta (contract with Idaho Power signed as Brisbie, LLC)
  • πŸ›οΈ Owned byMeta Platforms
  • πŸ‘€ Built forMeta
  • 🌳 Size485 acres
  • πŸ”Œ Where the power comes fromIdaho Power grid. Meta says it matches its power use with new solar farms southeast of Boise.
  • πŸ’§ WaterFarm water rights bought with the land; Meta paid for a new water and wastewater system it gave to the City of Kuna
  • ❄️ CoolingClosed-loop liquid cooling that reuses the same water
  • πŸ’΅ Cost$1.2 billion
  • πŸ’Έ Tax breaksIdaho's 2020 law removes sales tax on data center equipment for projects of at least $250 million that create at least 30 jobs. It is not public whether Meta uses it.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 8, 2026: We checked where the site is. OpenStreetMap maps the Meta Kuna Data Center as a fenced campus of about 360 acres in southeast Kuna. We put the pin in the middle of it. The 2025 satellite picture shows large data center buildings there; in 2018 it was farm fields.

What happened so far

  • Dec 2021
    Idaho Power asked state regulators to approve a special power contract for the data center (case IPC-E-21-42).
  • 2022
    Meta broke ground in Kuna.
  • May 11, 2023
    The Idaho Public Utilities Commission issued a final order in the power contract case.
  • Jan 2026
    Meta said building outsides were finished and about 1,400 workers were on site.
  • Sept 3, 2026
    Meta said the data center is open and fully running. It said it invested $1.2 billion.

Local votes and rules

πŸ—ΊοΈ Zoning change

The city council voted 3-2, with the mayor breaking a tie, to change about 620 acres of farmland in southeast Kuna to industrial use for Diode Ventures' Gemstone Technology Park data center campus.

April 1, 2025
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Meta opens new AI data center in Kuna, hopes to become 'water positive' Β· Idaho News 6 / CBS2 (idahonews.com) Β· Sept 3, 2026
  2. Meta's $1.2bn data center in Kuna, Idaho, goes live Β· DatacenterDynamics Β· Sept 2026
  3. How data centers are reshaping Idaho's farm country Β· Deseret News Β· March 4, 2026
  4. Meta hits 'peak construction' on $800M Idaho data center Β· Construction Equipment Guide (from Idaho Statesman) Β· Jan 2026
  5. Idaho Power requests special contract with enterprise data center Β· Idaho Power Β· Dec 2021
  6. Final Order No. 35777, case IPC-E-21-42 Β· Idaho Public Utilities Commission Β· May 11, 2023
  7. Meta Kuna Data Center (operator: Meta, landuse industrial / data centre) Β· OpenStreetMap Β· Oct 8, 2026
  8. Sentinel-2 cloudless 2025 satellite image of the site Β· EOX / Copernicus Sentinel-2 Β· Oct 8, 2026

See something wrong? Tell us and we'll fix it.