Projects
Hogansville data center (Hightower Road land)
Hogansville, Troup County
437 acres
🕒 Oct 2025: A resident's open records request revealed plans to sell 437 acres at $12,000 an acre fo…
Reported in the news, not confirmed yet
Being builtProject Pegasus data center campus (Google, LaGrange)
LaGrange, Troup County
for Google
🕒 Aug 12, 2026: The regional commission issued its finding on the second phase.
ProposedProject West data center campus (LaGrange)
LaGrange, Troup County
513 acres
🕒 March 7, 2025: Six-building campus on about 513 acres filed for state regional review (DRI #4414).
Local votes and rules
⏸️ Pause on new data centers · Unincorporated Troup County
Troup County commissioners paused all data center applications in the rural parts of the county for 90 days starting September 16, 2025. Staff will update the county's development rules. It does not cover LaGrange, Hogansville or West Point, or the data center already approved at the former Jindal site in LaGrange.
⏸️ Pause on new data centers · LaGrange
LaGrange City Council passed a temporary pause on new data centers in September 2025. Trackers list it as a 180-day pause.
Find your town
In Georgia, cities and towns decide inside their limits. Outside them, the county decides.