Being builtBig (AI-size): 350 megawatts

Project Pegasus data center campus (Google, LaGrange)

Also called: Project Pegasus, PRL2

Google is the company behind Project Pegasus, an $8 billion data center campus at 411 Pegasus Parkway in LaGrange. A 2026 state filing for a second building lists 350 megawatts and two to four million gallons of water a day.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of LaGrange City.

Where things stand: Being built Google named itself the owner in April 2026. A data center building already exists on site; a 470,000 sq ft second building was filed in July 2026.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 12, 2026): The regional commission issued its finding on the second phase.

What we know

  • 📍 Where411 Pegasus Parkway (industrial park), LaGrange, Troup County
  • 🏢 CompanyKDC (developer, per state filing)
  • 🏛️ Owned byGoogle (Alphabet)
  • 👤 Built forGoogle
  • ⚡ Power it needs350 megawatts (about as much as 280,000 homes)
  • 🔌 Where the power comes fromMEAG Power (350 MW listed in the 2026 filing).
  • 💧 WaterCity of LaGrange · 4,000,000 gallons a day
  • 💵 Cost$8 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will it really use 2 to 4 million gallons of water a day? 🙋 I'll find out ·
  • What tax break did the Development Authority of LaGrange give? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS aerial imagery of the site (32.984987, -85.055484): a large flat-roofed building with parking at the pin.

    What happened so far

    • 2024
      The $8 billion Project Pegasus was announced for LaGrange.
    • April 2026
      Google announced it is the owner and operator, its largest Georgia investment.
    • July 22, 2026
      A second phase (about 470,000 square feet) was filed for state regional review (DRI #4797).
    • Aug 12, 2026
      The regional commission issued its finding on the second phase.

    Local votes and rules

    ⏸️ Pause on new data centers

    LaGrange City Council passed a temporary pause on new data centers in September 2025. Trackers list it as a 180-day pause.

    Sept 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. What is Georgia's 'Project Pegasus'? Tech giant unveils $8 billion answer. · The Atlanta Journal-Constitution · April 2026
    2. DRI #4797: PRL2 (Development of Regional Impact filing) · Georgia Department of Community Affairs · July 22, 2026
    3. DRI #4797: PRL2, Additional Information Form · Georgia Department of Community Affairs · July 22, 2026
    4. DRI #4797 Initial Information Form: PRL2 (location field) · Georgia Department of Community Affairs · Oct 7, 2026
    5. Troup County tax parcel 0592 000004 (411 Pegasus Pkwy) (county parcel map service) · Troup County · Oct 7, 2026
    6. USGS National Map imagery around the existing pin · U.S. Geological Survey · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.