Project West data center campus (LaGrange)
Project West is a six-building, 600-megawatt data center campus planned on about 513 acres near LaGrange. The AJC reported a $9.7 billion investment over eight years; the state filing lists $6 billion.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of LaGrange City.
Where things stand: Proposed Filed for state review in March 2025. We found no later approval.
❓ 3 open questions about it: see below.
Last checked Oct 6, 2026.
🕒 Latest update (March 7, 2025): Six-building campus on about 513 acres filed for state regional review (DRI #4414).
What we know
- 📍 WhereLaGrange, Troup County
- 🏢 CompanyProject West WHP - GA LLC
- 🌳 Size513 acres
- ⚡ Power it needs600 megawatts (about as much as 480,000 homes)
- 🔌 Where the power comes fromPlans include its own electrical substation.
- 💧 WaterCity of LaGrange · 100,000 gallons a day
- 💵 Cost$9.7 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer and end user? 🙋 I'll find out ·
- Has LaGrange approved it? 🙋 I'll find out ·
- Was it affected by LaGrange's 180-day data center pause? 🙋 I'll find out ·
What happened so far
- March 7, 2025Six-building campus on about 513 acres filed for state regional review (DRI #4414).
Local votes and rules
⏸️ Pause on new data centers
LaGrange City Council passed a temporary pause on new data centers in September 2025. Trackers list it as a 180-day pause.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4414: Project West (Development of Regional Impact filing) · Georgia Department of Community Affairs · March 7, 2025
- DRI #4414: Project West, Additional Information Form · Georgia Department of Community Affairs · March 7, 2025
- Massive $9.7 billion data center proposed near LaGrange · The Atlanta Journal-Constitution · March 12, 2025