ProposedBig (AI-size): 600 megawatts

Project West data center campus (LaGrange)

Project West is a six-building, 600-megawatt data center campus planned on about 513 acres near LaGrange. The AJC reported a $9.7 billion investment over eight years; the state filing lists $6 billion.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of LaGrange City.

Where things stand: Proposed Filed for state review in March 2025. We found no later approval.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (March 7, 2025): Six-building campus on about 513 acres filed for state regional review (DRI #4414).

What we know

  • 📍 WhereLaGrange, Troup County
  • 🏢 CompanyProject West WHP - GA LLC
  • 🌳 Size513 acres
  • ⚡ Power it needs600 megawatts (about as much as 480,000 homes)
  • 🔌 Where the power comes fromPlans include its own electrical substation.
  • 💧 WaterCity of LaGrange · 100,000 gallons a day
  • 💵 Cost$9.7 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • March 7, 2025
      Six-building campus on about 513 acres filed for state regional review (DRI #4414).

    Local votes and rules

    ⏸️ Pause on new data centers

    LaGrange City Council passed a temporary pause on new data centers in September 2025. Trackers list it as a 180-day pause.

    Sept 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4414: Project West (Development of Regional Impact filing) · Georgia Department of Community Affairs · March 7, 2025
    2. DRI #4414: Project West, Additional Information Form · Georgia Department of Community Affairs · March 7, 2025
    3. Massive $9.7 billion data center proposed near LaGrange · The Atlanta Journal-Constitution · March 12, 2025

    See something wrong? Tell us and we'll fix it.