No project in Taylorsville Town, but 5 nearby
Who decides here: the Town Council of Taylorsville Town votes on zoning. The Polk County may review big projects too.
Nearby (within 15 miles)
Project Bunkhouse data center campus
Unincorporated Bartow County, Bartow County
π March 31, 2025: Project filed for state regional review (DRI #4433): about 8.7 million square feet of daβ¦
Proposedabout 11 miles awayKingston Technology Hub (Thor Equities)
Kingston, Bartow County
559 acres
π Sept 29, 2026: The regional commission issued its finding on the project.
Proposedabout 12 miles awaySwitch Atlanta North campus (KEEP 2.0)
Cartersville, Bartow County
126 acres
π Aug 29, 2023: City of Cartersville filed Switch's 126-acre data center for state regional review (DRI β¦
Proposedabout 13 miles awayProject Indo (DataBank)
Cartersville, Bartow County
69 acres
π July 15, 2026: The regional commission issued its finding on the project.
Status unclearabout 14 miles awayBrown Farm Road data center (Oakley Real Estate Partners)
Unincorporated Bartow County, Bartow County
111.4 acres
π Aug 24, 2026: Bartow County Planning Commission unanimously recommended denial of the rezoning.
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Taylorsville Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Georgia Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.