USA โ€บ Georgia โ€บ Bartow County โ€บ Kingston City
Proposed

Kingston Technology Hub (Thor Equities)

Also called: Kingston Area Data Center

Thor Equities wants to build one large data center building (about 350,000 square feet) on about 559 acres in Kingston. The filing says it would cost about $1 billion, need about 150 megawatts of power, and use about 50,000 gallons of water a day. It would need a rezoning from the city.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Filed for state regional review in Sept. 2026. The city must still decide on rezoning.

๐Ÿ•’ Latest update (Sept 29, 2026): The regional commission issued its finding on the project.

What we know

  • ๐Ÿ“ WhereWooded land off Georgia Highway 293, north of Cartersville, Kingston, Bartow County
  • ๐Ÿข CompanyThor Acquisition WC LLC
  • ๐Ÿ›๏ธ Owned byThor Equities
  • ๐ŸŒณ Size559 acres
  • โšก Power it needs150 megawatts (about as much as 120,000 homes)
  • ๐Ÿ”Œ Where the power comes fromPower would come from MEAG Power (the public power group for city-owned utilities). The filing says current power lines are not enough; a power study was requested.
  • ๐Ÿ’ง WaterBartow County Water Department ยท 50,000 gallons a day
  • ๐Ÿ’ต Cost$1 billion
  • ๐Ÿ‘ท Jobs promised50

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 4, 2026
    City of Kingston filed the project for state regional review (DRI #4835). It asks for a rezoning.
  • Sept 29, 2026
    The regional commission issued its finding on the project.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. DRI #4835: Kingston Technology Hub (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท Sept 4, 2026
  2. DRI #4835: Kingston Technology Hub, Additional Information Form ยท Georgia Department of Community Affairs ยท Sept 4, 2026
  3. Thor Equities Plans $1B Data Center In North Georgia: The Atlanta Deal Sheet ยท Bisnow ยท Sept 10, 2026

See something wrong? Tell us and we'll fix it.