Send us a tip
Approved, not built yetBig (AI-size): 150 megawatts

Kingston Technology Hub (Thor Equities)

Also called: Kingston Area Data Center

Thor Equities wants to build one large data center building (about 350,000 square feet) on about 559 acres in Kingston, along State Route 293. The state filing says it would cost about $1 billion, need about 150 megawatts of power, and use about 50,000 gallons of water a day. Kingston city leaders approved a special use permit on Nov. 2, 2026. No tenant has signed on yet.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Kingston City.

Where things stand: Approved, not built yet Kingston city leaders approved a special use permit on Nov. 2, 2026 (FOX 5). Residents say they plan to sue. We did not find a report on the annexation vote.

  • Nov 9, 2026: Our records now list Kingston Technology Hub (Thor Equities) as approved Source

❓ 7 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Nov 2, 2026): Kingston city leaders approved a special use permit for the Thor Equities data center along State Route 293 near Law Road. Residents said they have talked to lawyers and plan to sue.

What we know

  • 📍 WhereWooded land off Georgia Highway 293, north of Cartersville, Kingston, Bartow County
  • 🏢 CompanyThor Acquisition WC LLC
  • 🏛️ Owned byThor Equities
  • 🌳 Size559 acres
  • ⚡ Power it needs150 megawatts (about as much as 120,000 homes)
  • 🔌 Where the power comes fromPower would come from MEAG Power (the public power group for city-owned utilities). The filing says current power lines are not enough; a power study was requested.
  • 💧 WaterBartow County Water Department · 50,000 gallons a day
  • 💵 Cost$1 billion
  • 👷 Jobs promised50

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the end user (tenant)? 🙋 I'll find out ·
  • Will new power lines or a substation be built, and who pays? 🙋 I'll find out ·
  • Did any official sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Is the 561.51-acre annexation on the Kingston City Council agenda the Kingston Technology Hub site? 🙋 I'll find out ·
  • Did the city council approve the annexation of the 561.51 acres? 🙋 I'll find out ·
  • What was the Kingston City Council vote count on the special use permit? 🙋 I'll find out ·
  • Have residents filed a lawsuit against the Kingston approval? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 4, 2026
      City of Kingston filed the project for state regional review (DRI #4835). It asks for a rezoning.
    • Sept 29, 2026
      The regional commission issued its finding on the project.
    • Oct 26, 2026
      The Kingston Unified Zoning Board voted 2-1 to recommend a special use permit for the Thor Equities data center along State Route 293.
    • Nov 2, 2026
      Kingston city leaders approved a special use permit for the Thor Equities data center along State Route 293 near Law Road. Residents said they have talked to lawyers and plan to sue.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4835: Kingston Technology Hub (Development of Regional Impact filing) · Georgia Department of Community Affairs · Sept 4, 2026
    2. DRI #4835: Kingston Technology Hub, Additional Information Form · Georgia Department of Community Affairs · Sept 4, 2026
    3. Thor Equities Plans $1B Data Center In North Georgia: The Atlanta Deal Sheet · Bisnow · Sept 10, 2026
    4. DRI #4835 Initial Information Form: Kingston Technology Hub (location field) · Georgia Department of Community Affairs · Oct 7, 2026
    5. Bartow County tax parcel 0037-0197-001 (county parcel map service) · Bartow County · Oct 7, 2026
    6. City of Kingston: Notice of Public Hearings (annexation of 561.51 acres) · City of Kingston · Oct 2026
    7. Bartow County data center: Neighbors raise water, land concerns · FOX 5 Atlanta · Oct 27, 2026
    8. Kingston data center: City leaders approve special use permit · FOX 5 Atlanta · Nov 2, 2026

    See something wrong? Tell us and we'll fix it.