Project Bunkhouse is a plan for 12 data center buildings with about 8.7 million square feet of space in Bartow County. The state filing puts its value at $19 billion and its water use at about 625,000 gallons a day. It would be one of the largest projects in Georgia history.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Bartow County Board of Commissioners (for land outside city and town limits).
Where things stand: Proposed Filed for state review in March 2025. We found no final county vote.
❓ 4 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (March 31, 2025): Project filed for state regional review (DRI #4433): about 8.7 million square feet of data center buildings, $19 billion.
What we know
- 📍 WhereFarm land along Taff Road, south of Cartersville (per AJC), Unincorporated Bartow County, Bartow County
- 🏢 CompanyNot clearly named in the state filing
- 🌳 Size876.57 acres
- 💧 WaterBartow County Water Department · 625,000 gallons a day
- 💵 Cost$19 billion
- 💸 Tax breaksThe state filing says the project was negotiating tax incentives with the Bartow-Cartersville Joint Development Authority.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer and who is the end user? 🙋 I'll find out ·
- How much power will it need, and where will it come from? 🙋 I'll find out ·
- Has the county approved the rezoning? 🙋 I'll find out ·
- What tax break is being negotiated with the development authority? 🙋 I'll find out ·
What happened so far
- March 31, 2025Project filed for state regional review (DRI #4433): about 8.7 million square feet of data center buildings, $19 billion.
Local votes and rules
📜 Data center rules
Bartow County finished a data center ordinance in January 2025. It allows data centers with a 200-foot buffer from the property line and noise limits: 65 decibels by day and 55 decibels at night. County leaders say they welcome data centers.
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4433: Project Bunkhouse (Development of Regional Impact filing) · Georgia Department of Community Affairs · March 31, 2025
- DRI #4433: Project Bunkhouse, Additional Information Form · Georgia Department of Community Affairs · March 31, 2025
- $19B data center campus called 'Project Bunkhouse' proposed in Georgia · The Atlanta Journal-Constitution · April 2025