1 data center project in Calhoun City
Who decides here: the City Council of Calhoun City votes on zoning. The Gordon County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Dixon data center (Atlas Development)
Unincorporated Floyd County, Floyd County
178 acres
🕒 Feb 6, 2025: Atlas withdrew its request to rezone 178 acres for a data center of more than 2 million …
Reported in the news, not confirmed yet
Proposedabout 13 miles awayProject Springbank (Atlas Development)
Unincorporated Bartow County, Bartow County
630 acres
🕒 Feb 14, 2025: Atlas Development's six-building, 2.27 million square foot campus was filed for state re…
Being builtabout 13 miles awayCore Scientific Dalton 4 AI data center (Old Tilton Road)
Unincorporated Whitfield County, Whitfield County
170 acres
🕒 March 2026: Core Scientific posted that it is building a fourth, 250,000 sq ft data center on Old Ti…
Reported in the news, not confirmed yet
Local votes and rules
⏸️ Pause on new data centers
Calhoun's city council unanimously passed a pause on data center applications through July 27, 2026, before any proposal was filed. In June 2026 a developer was still pursuing a 500,000 square foot data center on 11 acres off Highway 53.
What you can do
- Get told first.
We'll email you if anything changes in Calhoun City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Calhoun City: Georgia Power Co. (company) or North Georgia Electric Member Corp. (co-op (owned by its members)) or City of Calhoun (run by the town).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Will Masterworks file a state regional review (DRI)?
- How much power and water would it use?
- Who is the end user?