Send us a tip
Proposed

Highway 53 data center (Masterworks Atlanta, Calhoun)

An Atlanta company, Masterworks Atlanta, wants to build a 500,000-square-foot data center off Highway 53 in Calhoun. The land is zoned industrial, but the city has paused data center approvals into 2027 while it studies rules.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Calhoun City.

Where things stand: Proposed Early stage. Calhoun has a pause (moratorium) on data center approvals until Jan. 1, 2027.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (June 8, 2026): Calhoun City Council extended its data center moratorium to Jan. 1, 2027.

What we know

  • 📍 Where11 acres of a 57-acre tract off Highway 53, across from St. Clement's Catholic Church, Calhoun, Gordon County
  • 🏢 CompanyMasterworks Atlanta
  • 🌳 Size57 acres
  • 👷 Jobs promised75

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 16, 2026
      City building official wrote that a data center would be an allowed use on the industrial land.
    • June 8, 2026
      Calhoun City Council extended its data center moratorium to Jan. 1, 2027.

    Local votes and rules

    ⏸️ Pause on new data centers

    Calhoun's city council unanimously passed a pause on data center applications through July 27, 2026, before any proposal was filed. In June 2026 a developer was still pursuing a 500,000 square foot data center on 11 acres off Highway 53.

    April 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Calhoun, Georgia, looks to understand what a 500K-square-foot data center's impact would be · Chattanooga Times Free Press · June 27, 2026
    2. OpenStreetMap: Saint Clement Catholic Church, 875 Rome Rd SW · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.