No project in Chattahoochee Hills City, but 22 nearby
Who decides here: the City Council of Chattahoochee Hills City votes on zoning. The Fulton County may review big projects too.
Nearby (within 15 miles)
T5 ATL IV data center (Coweta County site)
Unincorporated Coweta County, Coweta County
200 acres
🕒 May 5, 2025: T5 filed a different 'T5 ATL IV' project in the City of Fairburn (DRI #4465).
Proposedabout 8 miles awayRock House Road data center site
Unincorporated Douglas County, Douglas County
🕒 Sept 27, 2023: Four data center buildings (1.47 million square feet) and a substation filed for state r…
Proposedabout 8 miles awayAmazon Web Services land for data center (Echo Road, Douglas County)
Unincorporated Douglas County, Douglas County
118 acres · for Amazon Web Services
🕒 Oct 2024: Amazon confirmed it bought 118 acres in Douglas County and is exploring a data center th…
Reported in the news, not confirmed yet
Approved, not built yetabout 8 miles awayStream Data Centers Winston campus (SDC ATLA)
Unincorporated Douglas County, Douglas County
243 acres
🕒 July 2025: Douglas County commissioners approved the rezoning 3-2, minutes after the planning board…
Proposedabout 9 miles awayStack Infrastructure ATL02 campus (Lithia Springs)
Unincorporated Douglas County, Douglas County
39 acres
🕒 Nov 8, 2024: Stack filed an expansion with two more data centers and a substation (DRI #4326).
Approved, not built yetabout 9 miles awayWinston data center (Trammell Crow, Waldrop land)
Unincorporated Douglas County, Douglas County
🕒 2025: Douglas County commissioners approved the first Winston data center site by a single vot…
What you can do
- Get told first.
We'll email you if anything changes in Chattahoochee Hills City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Chattahoochee Hills City: Georgia Power Co. (company) or Greystone Power Corporation (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.