2 data center projects in Unincorporated DeKalb County
Who decides here: the DeKalb County Board of Commissioners decides on zoning for land outside city and town limits.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Unincorporated DeKalb County
Shadowbox Studios data center proposal
Unincorporated DeKalb County, DeKalb County
200 acres
🕒 Sept 9, 2026: DeKalb Zoning Board of Appeals affirmed the denial, leaving the matter to the courts.
Stopped or cancelledEllenwood data center (PCC-DeKalb LLC)
Unincorporated DeKalb County, DeKalb County
95 acres
🕒 Aug 13, 2026: DeKalb County Board of Commissioners rejected the data center after almost a year of res…
Reported in the news, not confirmed yet
Nearby (within 15 miles)
TA Realty data center (East Tanners Church Road)
Unincorporated Clayton County, Clayton County
🕒 June 2025: Development Authority of Clayton County approved a tax break for the $959 million project.
Reported in the news, not confirmed yet
Proposedabout 12 miles away1611 Ellsworth mixed-use project with data center
Atlanta, Fulton County
17.1 acres
🕒 Oct 21, 2025: The regional commission issued its finding on the project.
Proposedabout 12 miles awayRockdale Technology Park 1 (Sigman Road)
Unincorporated Rockdale County, Rockdale County
53 acres
🕒 Feb 15, 2024: Three data center buildings (837,500 square feet) filed for state regional review (DRI #…
Approved, not built yetabout 12 miles awayDC BLOX Atlanta East data center (Farmer Road)
Unincorporated Rockdale County, Rockdale County
🕒 Jan 17, 2024: DC Blox filed three data center buildings (about 1 million square feet) for state region…
Proposedabout 13 miles awayFort Gillem data center campus (Digital Realty ATL15/ATL16)
Forest Park, Clayton County
97 acres
🕒 Dec 2025: Crews found old buried material with white phosphorus that smoked when it hit the air. W…
Stopped or cancelledabout 13 miles awayProject Rockforge data center campus (Grind Capital / MMM Acquisitions)
Unincorporated Rockdale County, Rockdale County
263 acres
🕒 Oct 6, 2026: Rockdale County commissioners denied four requests for Project Rock Forge, including a l…
Built & runningabout 14 miles awayEdged Atlanta data center campus (ATL01)
Atlanta, Fulton County
🕒 Aug 2024: Edged opened its first building, ATL01-1 (27 MW).
Reported in the news, not confirmed yet
Local votes and rules
📌 Other
On Nov. 10, 2026, DeKalb commissioners voted 5-2 to withdraw a proposal that would have required an independent health and environmental study before the county could lift its data center pause. A separate proposal to define data centers by how they run, their power and water use, backup power and noise was put off to Dec. 15. The pause on new data center applications stays in place.
⚖️ Court case
Shadowbox Studios sued DeKalb County in August 2026, saying the county's data center pause is illegal and that planners told it three times in writing it could build a data center on its land. On September 9 the county zoning appeals board upheld the denial and left the fight to the courts.
✋ Turned down
After almost a year of protest, DeKalb County commissioners rejected a special land use permit for a 2 million square foot data center on 95 acres in Ellenwood, a mostly Black community already dealing with air pollution. County planners had recommended denial.
📜 Data center rules
DeKalb County commissioners voted down a proposed data center zoning ordinance after a year of work. Residents said the rules were not strong enough or would be hard to enforce. The draft sorted data centers into five size groups and kept big ones away from homes, parks and transit.
⏸️ Pause on new data centers
DeKalb County paused new data center applications in July 2025 to write rules, and has extended the pause several times. On July 7, 2026 commissioners extended it into early 2027 and asked county departments like public safety, roads and public health to study how data centers would affect them. The county cannot take new data center applications until March 30, 2027.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated DeKalb County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Unincorporated DeKalb County: Georgia Power Co. (company) or Walton Electric Member Corp. (co-op (owned by its members)) or Snapping Shoals El Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Will the developer appeal or sue?
- What will the court decide about the moratorium?
- How much of the nearly 200-acre property would the data center buildings cover?